PRJ-2026-004
Al-Khobar Branch — Rehabilitation & ExtensionPlanned to date 92%
- SPI
- 0.74
- Forecast finish
- 2027-02-03
- Budget
- SAR 412M
126 days lateMaterial risks: 2Open impediments: 3Corrective plan CP-2026-02
On-site handling of the Al-Khobar branch contractor’s distress.
Held on
27 October 202612:00 – 13:40
70 of 90 min
Overdue subcontractor payments
DiscussionKhalid N. Al-Mutairi
40 min
Underground tanks water-tightness test
DiscussionEng. Waleed O. Al-Juhani
30 min
Saved as you type
1. Overdue subcontractor payments
CTR-2024-0032. Underground tanks water-tightness test
ISS-0114No decisions recorded
Record the decision and put it to a vote if needed.
They show in the task register and on the owner’s calendar
ACT-0308Munirah A. Al-Khalidi
Project meeting — no quorum required
1 file
Drafted by the assistant from the agenda, the minutes, the decisions and the tasks. Review it before approval.
Shown only to invitees and the PMO, and leaves out what your permissions do not let you see.
Built automatically from the projects on the agenda: a card per project, the decisions needed, the support requested and the overdue tasks.
PRJ-2026-004
Al-Khobar Branch — Rehabilitation & ExtensionPlanned to date 92%
126 days lateMaterial risks: 2Open impediments: 3Corrective plan CP-2026-02
Nothing
ISS-0113 · Al-Khobar Branch — Rehabilitation & Extension
FundingSAR 6.4M· Asked from: Executive Committee
Approve paying four subcontractors directly from certificate 34, deducted from the main contractor
ACT-0307 · Khalid N. Al-Mutairi