On-site handling of the Al-Khobar branch contractor’s distress.

Held on

27 October 2026

12:00 – 13:40

  1. Held
  2. Minutes written
  3. Published
  4. Approved
Project meeting — no quorum required

Agenda

⁦70⁩ of ⁦90⁩ min

  1. Overdue subcontractor payments

    DiscussionKhalid N. Al-Mutairi

    ⁦40⁩ min

  2. Underground tanks water-tightness test

    DiscussionEng. Waleed O. Al-Juhani

    ⁦30⁩ min

Minutes

Saved as you type

  1. 1. Overdue subcontractor payments

    CTR-2024-003
  2. 2. Underground tanks water-tightness test

    ISS-0114

Decisions & votes

No decisions recorded

Record the decision and put it to a vote if needed.

Tasks

They show in the task register and on the owner’s calendar

Attendance & quorum

Project meeting — no quorum required

  • Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorGuestP-010t.alanazi@sca.saPresent
  • Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesGuestP-013b.alshammari@sca.saPresent
  • Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceGuestP-021w.aljuhani@sca.saPresent
  • Khalid N. Al-MutairiKhalid N. Al-MutairiSenior Finance & Procurement SpecialistGuestP-007k.almutairi@sca.saPresent
  • Eng. Mishari K. Al-OtaibiEng. Mishari K. Al-OtaibiDirector, Sustainability & Energy EfficiencyGuestP-028m.alotaibi@sca.saRemote

Attachments

⁦1⁩ file

  • Site-inspection-Oct-27.pdfEng. Waleed O. Al-Juhani · ⁦18.0⁩ MB

Smart minutes summaryAI-generated

Drafted by the assistant from the agenda, the minutes, the decisions and the tasks. Review it before approval.

Shown only to invitees and the PMO, and leaves out what your permissions do not let you see.

Meeting pack

Built automatically from the projects on the agenda: a card per project, the decisions needed, the support requested and the overdue tasks.

Project cards 1

Decisions needed

0

Nothing

Support requested

1
  • ISS-0113 · Al-Khobar Branch — Rehabilitation & Extension

    FundingSAR 6.4M· Asked from: Executive Committee

    Approve paying four subcontractors directly from certificate 34, deducted from the main contractor