PRJ-2026-002Off track4ExecutionConstruction

SCA Headquarters, Riyadh

Remove from watchlist

A 210,000 m² campus in Al-Malqa housing the Authority’s offices, the contractors’ service hall and the conference & exhibition building in six linked buildings, with multi-storey parking.

Early warning: ⁦88%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 1.2B

Actual cost

SAR 532.9M

⁦45%⁩ of budget

Progress

⁦42%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 1.3B

SAR +88.8M

SPI · CPI

0.82Schedule performance index · 0.820.93Cost performance index · 0.93

Forecast finish

⁦2027-09-12⁩

74 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure25 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate13 September 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate25 March 2027Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−21

May to October 2026

No material change in the health dimensions over the period.

AI insight

⁦88%⁩ chance of a further slip within ⁦60⁩ days

From the SPI trend (⁦0.82⁩), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.

Confidence⁦82%⁩

Copilot summary

Generated from the live project data

The project is behind plan: ⁦42%⁩ done against ⁦51%⁩ planned.

SPI ⁦0.82⁩, CPI ⁦0.93⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Specialised, Value-adding ServicesSO-3.1SCA services and programmes in every region

Main initiative

SI-3.1.2HQ & major qualification centres

Contribution to the initiative⁦58%⁩

The project’s share of the initiative’s project budget (3 projects)

Secondary links

Annual work-plan line
WP-2024-002
Classification
Strategic

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦42%⁩

Awaiting acceptance ⁦11%⁩

Not handed in ⁦47%⁩

5 deliverables accepted

  • Site works & excavation⁦18%⁩
  • Detailed design⁦8%⁩
  • Permits & approvals⁦8%⁩
  • Project plan & baseline⁦4%⁩
  • Monitoring & reporting⁦4%⁩

1 deliverable under inspection or acceptance

  • Structure⁦11%⁩

Corrective plan requiredThe project is seriously late (74 days late · SPI ⁦0.82⁩) and has no corrective plan yet.

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦93%⁩ of budget

532.9M/ 1.2B88.8Mprojected overrun(⁦7.5%⁩)
Actual spend
532.9M
Committed
1.1B
Approved budget
1.2B
Estimate at completion
1.3B

Next milestones

  • Provisional acceptance⁦2027-05-20⁩was ⁦2027-03-25⁩Late
  • Closure⁦2027-09-12⁩was ⁦2027-06-30⁩Late

Waiting on someone

⁦1⁩ approval and ⁦2⁩ open actions on this project

Approvals & requests

From «My actions» for this project

Actions

⁦2⁩ open

  • Ask the Saudi Electricity Company to divert the HV lineEng. Bandar M. Al-Shammari3 days overdue2026-10-2514 Jumada I 1448 AHHigh
  • Analyse the budget impact of price adjustmentsHaifa S. Al-RuwailiIn 13 days2026-11-1030 Jumada I 1448 AHHigh

Risks & impediments

4 open risks, exposure SAR 101.5M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩1Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩RSK-0015Steel and concrete price rises driving price-adjustment claimsProbability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩1Probability: Likely · Impact: MajorHigh · Score ⁦16⁩RSK-0017Contractor claim for a 120-day extension with compensation1Probability: Likely · Impact: SevereCritical · Score ⁦20⁩RSK-0016Late handover of the northern plot and utility diversions in zones 3 and 4
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩1Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩RSK-0018Safety incidents around cranes and deep excavations
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical2
  • High1
  • Medium1
  • Low0

Deliverables

⁦5⁩ of ⁦12⁩ approved

  • Project plan & baseline002-D1 · V1 · CRT-002-01⁦4%⁩Eng. Ahmed Y. Asiri⁦2024-08-04⁩2024-08-0429 Muharram 1446 AHApproved
  • Monitoring & reporting002-D2 · V1 · CRT-002-02⁦4%⁩Eng. Bandar M. Al-Shammari⁦2024-11-09⁩2024-11-097 Jumada I 1446 AHApproved
  • Detailed design002-D3 · V1 · CRT-002-03⁦8%⁩Eng. Bandar M. Al-Shammari⁦2025-02-13⁩2025-02-1314 Shaʻban 1446 AHApproved
  • Permits & approvals002-D4 · V1 · CRT-002-04⁦8%⁩Eng. Turki A. Al-Anazi⁦2025-05-20⁩2025-05-2022 Dhuʻl-Qiʻdah 1446 AHApproved
  • Site works & excavation002-D5 · V1 · CRT-002-05⁦18%⁩Eng. Turki A. Al-Anazi⁦2025-08-25⁩2025-08-252 Rabiʻ I 1447 AHApproved
  • Structure002-D6 · V1⁦11%⁩Eng. Ahmed Y. Asiri333 days overdue2025-11-298 Jumada II 1447 AHIn review
  • Finishes002-D7 · V0⁦11%⁩Eng. Bandar M. Al-Shammari237 days overdue2026-03-0516 Ramadan 1447 AHDraft
  • Supply002-D8 · V0⁦8%⁩Eng. Ahmed Y. Asiri140 days overdue2026-06-1024 Dhuʻl-Hijjah 1447 AHDraft
  • Installation002-D9 · V0⁦8%⁩Eng. Bandar M. Al-Shammari44 days overdue2026-09-143 Rabiʻ II 1448 AHDraft
  • Testing & commissioning002-D10 · V0⁦8%⁩Eng. Turki A. Al-AnaziIn 52 days2026-12-1910 Rajab 1448 AHDraft
  • Provisional acceptance002-D11 · V0⁦6%⁩Eng. Bandar M. Al-ShammariIn 149 days2027-03-2618 Shawwal 1448 AHDraft
  • Final acceptance002-D12 · V0⁦6%⁩Eng. Turki A. Al-AnaziIn 245 days2027-06-3025 Muharram 1449 AHDraft

Team, contracts & documents

Team

4 members

Eng. Ahmed Y. Asiri · Director, Construction ProjectsEng. Turki A. Al-Anazi · Head, Qualification & Training SectorHaifa S. Al-Ruwaili · Senior Financial Analyst
  • Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsProject managerP-020a.asiri@sca.sa⁦60%⁩
  • Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorProject sponsorP-010t.alanazi@sca.sa⁦20%⁩
  • Haifa S. Al-RuwailiHaifa S. Al-RuwailiSenior Financial AnalystFinancial analystP-037h.alruwaili@sca.sa⁦15%⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close