AI insight
88% chance of a further slip within 60 days
From the SPI trend (0.82), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.
A 210,000 m² campus in Al-Malqa housing the Authority’s offices, the contractors’ service hall and the conference & exhibition building in six linked buildings, with multi-storey parking.
Budget (BAC)
Actual cost
45% of budget
Progress
Estimate at completion
SAR +88.8M
SPI · CPI
Forecast finish
74 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure25 March 2027
A weighted index, not just percent complete; each dimension leads to the tab that explains it.
Health index
60
Weak — act now
Index over the last six reports
May to October 2026
No material change in the health dimensions over the period.
AI insight
From the SPI trend (0.82), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.
Generated from the live project data
The project is behind plan: 42% done against 51% planned.
SPI 0.82, CPI 0.93.
How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.
The main objective and initiative, the secondary links, and the project’s contribution to its initiative.
Main initiative
SI-3.1.2HQ & major qualification centres
The project’s share of the initiative’s project budget (3 projects)
Secondary links
Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.
Counted
42%Awaiting acceptance 11%
Not handed in 47%
5 deliverables accepted
1 deliverable under inspection or acceptance
Corrective plan requiredThe project is seriously late (74 days late · SPI 0.82) and has no corrective plan yet.
3 of 5 milestones complete
Earned-value curve
Planned, earned and actual to the data date, cumulative, with the forecast cost tail
Commitments are 93% of budget
1 approval and 2 open actions on this project
From «My actions» for this project
2 open
Cost and schedule impact
4 open risks, exposure SAR 101.5M
Impact
1 escalated
5 of 12 approved
4 members