PRJ-2026-002Off track4ExecutionConstruction

SCA Headquarters, Riyadh

Remove from watchlist

A 210,000 m² campus in Al-Malqa housing the Authority’s offices, the contractors’ service hall and the conference & exhibition building in six linked buildings, with multi-storey parking.

Early warning: ⁦88%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 1.2B

Actual cost

SAR 532.9M

⁦45%⁩ of budget

Progress

⁦42%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 1.3B

SAR +88.8M

SPI · CPI

0.82Schedule performance index · 0.820.93Cost performance index · 0.93

Forecast finish

⁦2027-09-12⁩

74 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure25 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate13 September 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate25 March 2027Closure · Not startedClosure · Not started

Periodic update cards

Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.

Period

October 2026

In approvalDue todayAction time limit about to lapse · Limit 2 working days
Progress
⁦42%⁩
Planned
⁦51%⁩
SPI
0.82
Open the card

Periodic update cards

PeriodStatusProgressCurrent stepDate
October 2026UPD-002-2026-10In approval⁦42%⁩Methodology reviewDr. Noura M. Al-OtaibiDue todayAction time limit about to lapse · Limit 2 working days⁦2026-10-26⁩
September 2026UPD-002-2026-09Approved⁦40%⁩—⁦2026-10-02⁩
August 2026UPD-002-2026-08Approved⁦37%⁩—⁦2026-09-02⁩