Saudi Contractors AuthorityMunjaz11My actionsNotifications

Programme · PG-07 · Headquarters & Regional Centres Portfolio

Headquarters & Major Qualification Centres Programme

Off track

The SCA headquarters and the qualification centres in Qassim, Asir and Arar.

Approved budget
SAR 2.3B

incl. SAR 40M programme reserve

Actual spend
SAR 784.9M

⁦34%⁩ of budget

EAC
SAR 2.4B+5.1%

Estimate at completion

Progress
⁦31%⁩

Planned ⁦37%⁩

Schedule performance index
0.87

Cost performance index 0.95

Manager

Eng. Ahmed Y. Asiri

Director, Construction Projects

Sponsor

Eng. Bandar M. Al-Shammari

Director General, Facilities & Premises

Projects

4 projects

2024-03-03 — 2028-12-31

On track 1At risk 1Off track 2

Programme objectives

What the programme must achieve, and the strategic objectives it serves.

  1. 1

    A headquarters and major qualification centres in Riyadh, Qassim, Asir and the Northern Borders

  2. 2

    Fit out 120 training & test halls a year to 2028

  3. 3

    A branch or qualification centre within 150 km of 78% of member contractors

Programme benefits

From baseline to target

  • Training & test halls fitted out this year

    by ⁦2026⁩
    Baseline 0Current 97 hallsTarget 120
  • Contractors within 150 km of a branch or centre

    by ⁦2027⁩
    Baseline 71Current 76.4 %Target 78
  • Rent avoided (cumulative to 2035)

    by ⁦2028⁩
    Baseline 0Current 610 SAR MTarget 900

Roadmap

One lane per project: start to forecast finish, with the progress earned and the baseline finish.

EarnedRemainingBaseline finishSlip
20242025202620272028
2027-09-12
2027-08-03
2027-09-28
2028-12-31

Dependencies between projects

What waits on what. Red links are on the programme’s critical path.

Critical path

What each project needs from the one before

  • Critical

    The standard training-hall layout is proven in Qassim before it is fixed for the HQ

  • Critical

    The Arar complex applies the design standards approved for the HQ

Shared risks

Risks that hit more than one project, managed at programme level.

20

Late land allocation and handover for Buraydah and the HQ

PRK-07-1·Escalate·Eng. Ahmed Y. Asiri

Affects
12

Steel and ready-mix shortages at the peak of the season

PRK-07-2·Mitigate·Eng. Ahmed Y. Asiri

Affects

Open risks in the programme’s projects

8 risks

Open risks in the programme’s projects
  • Critical3
  • High3
  • Medium2
  • Low0
  • Risks 8
Probability
5
4
3
2
1
12345

Impact

Open risks in the programme’s projects
Probability \ Impact12345
50 · Low0 · Medium0 · High1 · Critical0 · Critical
40 · Low0 · Medium0 · Medium2 · High2 · Critical
30 · Low0 · Low0 · Medium1 · Medium1 · High
20 · Low0 · Low0 · Low0 · Medium1 · Medium
10 · Low0 · Low0 · Low0 · Low0 · Low

Programme KPIs · Stakeholders

Stakeholders

Power against interest; click a person to see their role.

Power

Keep satisfied0

Manage closely5

Monitor0

Keep informed0

Eng. Bandar M. Al-ShammariManage closelyEng. Turki A. Al-AnaziManage closelyYousef A. Al-OmariManage closelyEng. Waleed O. Al-JuhaniManage closelyMunirah A. Al-KhalidiManage closely

Interest

Programme decisions

What the committees decided on the programme’s projects, and what the programme raised to them.

Committees

Projects Steering Committee

Monthly · Quorum ⁦5⁩

Dr. Mohammed I. Al-Subaie · Head, Strategy & Institutional Excellence SectorEng. Turki A. Al-Anazi · Head, Qualification & Training SectorEng. Majed S. Al-Rasheed · Head, Digital Transformation Sector
Chair: Dr. Abdullah S. Al-QahtaniNext meeting 2026-11-03
Executive Committee

Weekly · Quorum ⁦4⁩

Dr. Mohammed I. Al-Subaie · Head, Strategy & Institutional Excellence SectorEng. Turki A. Al-Anazi · Head, Qualification & Training SectorEng. Majed S. Al-Rasheed · Head, Digital Transformation SectorSarah A. Al-Qarni · Head, Corporate Support Sector
Chair: Dr. Abdullah S. Al-QahtaniNext meeting 2026-10-28
Bid Evaluation & Award Committee

As needed · Quorum ⁦3⁩

Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistMazen A. Al-Hazmi · Procurement & Tendering SpecialistEng. Ibrahim A. Al-Ghamdi · Director, Engineering SupervisionEng. Asma S. Al-Hamdan · Enterprise Architect
Chair: Munirah A. Al-KhalidiNo meeting scheduled

Programme projects

The programme’s performance is computed from these projects.

⁦4⁩ results
Export CSV
Manager
SCA Headquarters, RiyadhPRJ-2026-002Eng. Ahmed Y. Asiri4ExecutionOff track⁦42%⁩1.2B1.3B⁦+7.5%⁩0.82Schedule performance index · 0.820.93Cost performance index · 0.93
Qassim Vocational Qualification CentrePRJ-2026-020Eng. Ahmed Y. Asiri4ExecutionOff track⁦44%⁩345M363.2M⁦+5.3%⁩0.80Schedule performance index · 0.800.95Cost performance index · 0.95
Asir Vocational Qualification CentrePRJ-2026-021Eng. Ibrahim A. Al-Ghamdi3PlanningOn track⁦2%⁩520M520M⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00
Arar Vocational Qualification CentrePRJ-2026-034Eng. Ibrahim A. Al-Ghamdi4ExecutionAt risk⁦33%⁩238M247.9M⁦+4.2%⁩0.89Schedule performance index · 0.890.96Cost performance index · 0.96
Total · 42.3B2.4B
⁦1⁩–⁦4⁩ of ⁦4⁩

Budget shares

Budget shares

SAR 2.3B

Budget

  • SCA Headquarters, RiyadhSAR 1.2B⁦52%⁩
  • Qassim Vocational Qualification CentreSAR 345M⁦15%⁩
  • Asir Vocational Qualification CentreSAR 520M⁦23%⁩
  • Arar Vocational Qualification CentreSAR 238M⁦10%⁩
Budget shares
CategoryValueShare
SCA Headquarters, RiyadhSAR 1.2B⁦52%⁩
Qassim Vocational Qualification CentreSAR 345M⁦15%⁩
Asir Vocational Qualification CentreSAR 520M⁦23%⁩
Arar Vocational Qualification CentreSAR 238M⁦10%⁩
TotalSAR 2.3B⁦100%⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close