Late land allocation and handover for Buraydah and the HQ
PRK-07-1·Escalate·Eng. Ahmed Y. Asiri
Programme · PG-07 · Headquarters & Regional Centres Portfolio
The SCA headquarters and the qualification centres in Qassim, Asir and Arar.
incl. SAR 40M programme reserve
34% of budget
Estimate at completion
Planned 37%
Cost performance index 0.95
Manager
Eng. Ahmed Y. Asiri
Director, Construction Projects
Sponsor
Eng. Bandar M. Al-Shammari
Director General, Facilities & Premises
Projects
4 projects
2024-03-03 — 2028-12-31
On track 1At risk 1Off track 2
What the programme must achieve, and the strategic objectives it serves.
A headquarters and major qualification centres in Riyadh, Qassim, Asir and the Northern Borders
Fit out 120 training & test halls a year to 2028
A branch or qualification centre within 150 km of 78% of member contractors
From baseline to target
Training & test halls fitted out this year
by 2026Contractors within 150 km of a branch or centre
by 2027Rent avoided (cumulative to 2035)
by 2028One lane per project: start to forecast finish, with the progress earned and the baseline finish.
What waits on what. Red links are on the programme’s critical path.
Critical path
Critical
The standard training-hall layout is proven in Qassim before it is fixed for the HQ
Critical
The Arar complex applies the design standards approved for the HQ
Risks that hit more than one project, managed at programme level.
Late land allocation and handover for Buraydah and the HQ
PRK-07-1·Escalate·Eng. Ahmed Y. Asiri
Steel and ready-mix shortages at the peak of the season
PRK-07-2·Mitigate·Eng. Ahmed Y. Asiri
8 risks
Impact
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 0 · Low | 0 · Medium | 0 · High | 1 · Critical | 0 · Critical |
| 4 | 0 · Low | 0 · Medium | 0 · Medium | 2 · High | 2 · Critical |
| 3 | 0 · Low | 0 · Low | 0 · Medium | 1 · Medium | 1 · High |
| 2 | 0 · Low | 0 · Low | 0 · Low | 0 · Medium | 1 · Medium |
| 1 | 0 · Low | 0 · Low | 0 · Low | 0 · Low | 0 · Low |
Training and test halls fitted out this year (cumulative)
97halls
+9
Target 12081%
Premises and centre projects delivered to plan
73%
+1
Target 85%86%
Contractors within 150 km of a branch or qualification centre
76.4%
+1
Target 78.0%98%
Contracts won by Irtiqaa beneficiaries (cumulative)
1,810SAR M
+230
Target 2,40075%
Power against interest; click a person to see their role.
Keep satisfied0
Manage closely5
Monitor0
Keep informed0
Interest
What the committees decided on the programme’s projects, and what the programme raised to them.
Committees
Monthly · Quorum 5
Members
6 members
Weekly · Quorum 4
As needed · Quorum 3
The programme’s performance is computed from these projects.
Display options
| Manager | ||||||||
|---|---|---|---|---|---|---|---|---|
| SCA Headquarters, RiyadhPRJ-2026-002 | Eng. Ahmed Y. Asiri | 4Execution | Off track | 42% | 1.2B | 1.3B+7.5% | 0.82Schedule performance index · 0.82 | 0.93Cost performance index · 0.93 |
| Qassim Vocational Qualification CentrePRJ-2026-020 | Eng. Ahmed Y. Asiri | 4Execution | Off track | 44% | 345M | 363.2M+5.3% | 0.80Schedule performance index · 0.80 | 0.95Cost performance index · 0.95 |
| Asir Vocational Qualification CentrePRJ-2026-021 | Eng. Ibrahim A. Al-Ghamdi | 3Planning | On track | 2% | 520M | 520M0.0% | 1.00Schedule performance index · 1.00 | 1.00Cost performance index · 1.00 |
| Arar Vocational Qualification CentrePRJ-2026-034 | Eng. Ibrahim A. Al-Ghamdi | 4Execution | At risk | 33% | 238M | 247.9M+4.2% | 0.89Schedule performance index · 0.89 | 0.96Cost performance index · 0.96 |
| Total · 4 | 2.3B | 2.4B |
SAR 2.3B
Budget
| Category | Value | Share |
|---|---|---|
| SCA Headquarters, Riyadh | SAR 1.2B | 52% |
| Qassim Vocational Qualification Centre | SAR 345M | 15% |
| Asir Vocational Qualification Centre | SAR 520M | 23% |
| Arar Vocational Qualification Centre | SAR 238M | 10% |
| Total | SAR 2.3B | 100% |