Saudi Contractors Authority Strategy — Building the Future with Confidence

Premises and centre projects delivered to plan

Off trackApproved

SCA services and programmes in every region·Specialised, Value-adding Services

Actual · October

73%

2026 target

⁦85%⁩

Attainment

⁦86%⁩

Year-end forecast

⁦75%⁩

Forecast gap to target

⁦10%⁩

The path from baseline to 2030

Where the KPI stands today between its baseline, this year’s target and the 2030 target.

Baseline

⁦62%⁩

Today

⁦73%⁩

2026 target

⁦85%⁩

2030 target

⁦95%⁩

Left to the 2026 target
⁦12%⁩⁦48%⁩ of the way covered
Left to the 2030 target
⁦22%⁩⁦33%⁩ of the way covered

Monthly series and forecast

January – October measured, November and December forecast with a confidence band; the gold line is the 2026 target.

Monthly series and forecast
  • Actual
  • Baseline
  • Forecast
  • Forecast range
Monthly series and forecast
PeriodActualBaseline
Jan66 %62 %
Feb67 %62 %
Mar68 %62 %
Apr68 %62 %
May69 %62 %
Jun70 %62 %
Jul70 %62 %
Aug71 %62 %
Sep72 %62 %
Oct73 %62 %
Nov (Forecast)74 %62 %
Dec (Forecast)75 %62 %

Measurement history

Every reading with who entered it, its evidence and its approval. Formal measurement points are marked.

PeriodValueOf targetKindStateEntered byEvidence
October 202673⁦86%⁩Formal measurementApprovedEng. Bandar M. Al-Shammari2026-10-27K-3.1.1_2026-10.pdf
September 202672⁦85%⁩Formal measurementApprovedEng. Bandar M. Al-Shammari2026-10-05K-3.1.1_2026-09.pdf
August 202671⁦84%⁩Formal measurementApprovedEng. Bandar M. Al-Shammari2026-09-04K-3.1.1_2026-08.pdf
July 202670⁦82%⁩Formal measurementApprovedEng. Bandar M. Al-Shammari2026-08-07K-3.1.1_2026-07.pdf
June 202670⁦82%⁩Formal measurementApprovedEng. Bandar M. Al-Shammari2026-07-06K-3.1.1_2026-06.pdf
May 202669⁦81%⁩Formal measurementApprovedEng. Bandar M. Al-Shammari2026-06-05K-3.1.1_2026-05.pdf
April 202668⁦80%⁩Formal measurementApprovedEng. Bandar M. Al-Shammari2026-05-04K-3.1.1_2026-04.pdf
March 202668⁦80%⁩Formal measurementApprovedEng. Bandar M. Al-Shammari2026-04-07K-3.1.1_2026-03.pdf
February 202667⁦79%⁩Formal measurementApprovedEng. Bandar M. Al-Shammari2026-03-06K-3.1.1_2026-02.pdf
January 202666⁦78%⁩Formal measurementApprovedEng. Bandar M. Al-Shammari2026-02-05K-3.1.1_2026-01.pdf

Contributing projects

The projects that move this KPI, and each one’s share of the effect by budget size.

AI insight

Closing the gap runs through one project

The project with the most weight on this KPI is “SCA Headquarters, Riyadh”, with ⁦77%⁩ of the linked budget, and it is Off track. Speeding it up is the fastest way to close the gap before December.

Confidence⁦78%⁩

Corrective actions

What we are doing to bring the KPI back on track, who owns it, and by when.

  • Speed up the handover of the HQ site’s northern plot with the municipality and the utility owners

    Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.saDue ⁦2026-10-20⁩8 days overdue2026-10-209 Jumada I 1448 AHSCA Headquarters, Riyadh
    Overdue
  • Take the conference & exhibition building fit-out out of the HQ construction contract and tender it separately

    Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.saDue ⁦2026-11-30⁩In 33 days2026-11-3020 Jumada II 1448 AHSCA Headquarters, Riyadh
    In progress

Comments

The owner, the Performance Measurement Office and leadership discussing the readings.

No comments yet. Start the discussion on this KPI.