PRJ-2026-002Off track4ExecutionConstruction

SCA Headquarters, Riyadh

Remove from watchlist

A 210,000 m² campus in Al-Malqa housing the Authority’s offices, the contractors’ service hall and the conference & exhibition building in six linked buildings, with multi-storey parking.

Early warning: ⁦88%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 1.2B

Actual cost

SAR 532.9M

⁦45%⁩ of budget

Progress

⁦42%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 1.3B

SAR +88.8M

SPI · CPI

0.82Schedule performance index · 0.820.93Cost performance index · 0.93

Forecast finish

⁦2027-09-12⁩

74 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure25 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate13 September 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate25 March 2027Closure · Not startedClosure · Not started