RSK-0016SCA Headquarters, Riyadh

Late handover of the northern plot and utility diversions in zones 3 and 4

20CriticalEscalatedMaterial

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Late handover of the northern part of the site, and utility diversions in zones 3 and 4

Preventive controls

  • A joint committee with the Saudi Electricity Company to schedule the diversions
  • Re-sequence works to start with zones 1 and 2

1 / 2

Event

Late handover of the northern plot and utility diversions in zones 3 and 4

20CriticalTrigger

No part of the land handed over before the end of November

Contingency

Move laydown areas and site offices to zone 2 until the land is fully handed over

Impact

The conferences & exhibitions building and its linked buildings at least 75 days late, and extension claims from the contractor

SAR 31M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
20Critical

Residual

5
4
3
2
1
1
2
3
4
5
12Medium

Exposure

SAR 31M

Residual

⁦40⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 4 days ago

  1. Project manager

    Eng. Ahmed Y. Asiri

    Currently followed up here
  2. Programme manager

    Current level

    Eng. Ahmed Y. Asiri

    Automatically at 15 days unreviewed · in 11 days
  3. 3

    PMO director

    Dr. Noura M. Al-Otaibi

    Automatically at 20 days unreviewed · in 16 days
  4. 4

    Executive committee

    Dr. Abdullah S. Al-Qahtani

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦1⁩ of ⁦2⁩ done
  • A joint committee with the Saudi Electricity Company to schedule the diversions

    Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.sa
    In progressIn 8 days2026-11-0525 Jumada I 1448 AH
  • Re-sequence works to start with zones 1 and 2

    Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa
    Done⁦2026-10-15⁩2026-10-154 Jumada I 1448 AH

Trigger

No part of the land handed over before the end of November

Contingency

Move laydown areas and site offices to zone 2 until the land is fully handed over