CR-2026-002SCA Headquarters, Riyadh

Add a third basement level to the conference & exhibition building

ScopeApprovedImpact level: Major

Justification and the cost, schedule and risk impact, with a recommendation.

Electronic form

Impact analysis

Before and after — as it will show in the baseline if approved

Cost

+SAR 38.5M

Current budgetSAR 1.1B

After the changeSAR 1.2B

+3.4%

Schedule

+⁦60⁩ d
  • Baseline finish2027-05-01
  • New finish2027-06-30

Risk

+3
9Medium12Medium
Risk RSK-0017 · Contractor claim for a 120-day extension with compensation

Raises the chance of extension claims

Benefits

+9%

420 more parking spaces for visitors and staff

⁦+9⁩% of expected benefits

Reason for change

An updated parking study expects a shortfall for visitors and staff once the conference & exhibition building opens and hosts the Future Projects Forum

Justification

Building it now costs about 60% less than a car-park building later, and eases congestion around HQ

PMO recommendation

Approve with conditions

The PMO recommends approval with a fixed unit rate for the concrete works

Conditions

  • Fix the unit rate for concrete works

Approval workflow

  1. Submitted

    Eng. Ahmed Y. Asiri

    Done2026-03-02

  2. PM review

    Eng. Ahmed Y. Asiri

    Done2026-03-03

  3. Impact analysis

    Karim Haddad

    Done2026-03-07

  4. Finance & procurement

    Munirah A. Al-Khalidi

    Done2026-03-08

  5. Project owner’s acceptance

    Eng. Bandar M. Al-Shammari

    Done2026-03-08

  6. Change committee recommendation

    Dr. Mohammed I. Al-Subaie

    Done2026-03-19

  7. Executive Committee decision

    Dr. Abdullah S. Al-Qahtani

    Done2026-03-22

  8. Baseline updated

    Eng. Ahmed Y. Asiri

    Done2026-03-26

Why this route

The route is built from the request’s kind and impact level under the approved authority matrix.

Impact levelMajorAbove SAR 5M or 90 days

  • A cost impact of SAR 38.5M is above SAR 5M — «major»: the Change Committee recommends and the Executive Committee decides.
  • It has a financial link, so Finance & Procurement take part before the decision.
  • It changes scope or deliverables, so the project owner must accept it.

Change committee vote

Members vote before or during the meeting; the decision is taken once quorum is met

  • Dr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorDr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorP-009m.alsubaie@sca.saChairApprove
  • Dr. Noura M. Al-OtaibiDirector, Project Management OfficeDr. Noura M. Al-OtaibiDirector, Project Management OfficeP-002n.alotaibi@sca.saYouApprove
  • Khalid N. Al-MutairiSenior Finance & Procurement SpecialistKhalid N. Al-MutairiSenior Finance & Procurement SpecialistP-007k.almutairi@sca.saApprove
  • Munirah A. Al-KhalidiDirector General, Finance & ProcurementMunirah A. Al-KhalidiDirector General, Finance & ProcurementP-018m.alkhalidi@sca.saApprove
  • Eng. Asma S. Al-HamdanEnterprise ArchitectEng. Asma S. Al-HamdanEnterprise ArchitectP-031a.alhamdan@sca.saApprove
  • Eng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@sca.saApprove
6/6Quorum met
  • Approve6
  • Approve with conditions0
  • Reject0
  • Abstain0

Decided by the committee on 22 March 2026The decision in the log · DEC-2026-009

Baseline

Baseline updated on 26 March 2026