Execution
Change request
The change, its impact analysis and the approval decision
- Form no.
- SCA-PMO-F09
- Template edition
- 3.1
- Version
- V2
- Form date
- 2026-03-02
- Hijri
- 13 Ramadan 1447 AH
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-002
- Project
- SCA Headquarters, Riyadh
- Portfolio
- Headquarters & Regional Centres Portfolio
- Sector
- Corporate Support Sector
- Sponsor
- Eng. Turki A. Al-Anazi
- Project manager
- Eng. Ahmed Y. Asiri
1The change
- TitleAuto-filled
- Add a third basement level to the conference & exhibition building
- KindAuto-filled
- Scope
- Requested byAuto-filled
- Eng. Ahmed Y. Asiri
- Raised onAuto-filled
- 2026-03-02
Reason
An updated parking study expects a shortfall for visitors and staff once the conference & exhibition building opens and hosts the Future Projects Forum
Justification
Building it now costs about 60% less than a car-park building later, and eases congestion around HQ
2Impact analysis
Cost
SAR +38.5M
Schedule
+60 days
Risk
9 → 12
Benefits
+9%
Risk impact
Raises the chance of extension claims
Benefits impact
420 more parking spaces for visitors and staff
3The approval decision
The PMO’s recommendation
The PMO recommends approval with a fixed unit rate for the concrete works
- Change Committee decision
- Approve with conditions
- Decided on
- 2026-03-22
- Decision number
- DEC-2026-009
Conditions
- Fix the unit rate for concrete works
Approval logChain: Change request approval · version 5
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Ahmed Y. AsiriDirector, Construction Projects | Submitted | — | 2026-03-02 11:26 |
| 2 | Project manager | Technical acceptance | Eng. Ahmed Y. AsiriProject manager | Approved | — | 2026-03-03 13:10 |
| 3 | PMO review & impact analysis | Methodology review | Ghada A. Al-ShahraniPMO — analyst | Approved | — | 2026-03-05 14:17 |
| 4 | Financial impact | Financial approval | Munirah A. Al-KhalidiFinance | Approved | — | 2026-03-09 12:45 |
| 5 | Contractual impact | Financial approval | Mazen A. Al-HazmiProcurement & contracts | Approved | — | 2026-03-10 13:22 |
| 6 | Change Committee | Technical acceptance | Dr. Mohammed I. Al-SubaieChange Committee | Approved | — | 2026-03-15 11:38 |
| 7 | Projects Steering Committee | Technical acceptance | Approval engineProjects Steering Committee | Pre-breach alert | — | 2026-03-25 08:00 |
| 8 | Projects Steering Committee | Technical acceptance | Dr. Abdullah S. Al-QahtaniProjects Steering Committee | Approved | — | 2026-03-26 14:53 |
Signatures
Project manager
Eng. Ahmed Y. Asiri
Approved2026-03-03
PMO review & impact analysis
Ghada A. Al-Shahrani
Approved2026-03-05
Financial impact
Munirah A. Al-Khalidi
Approved2026-03-09
Contractual impact
Mazen A. Al-Hazmi
Approved2026-03-10
Change Committee
Dr. Mohammed I. Al-Subaie
Approved2026-03-15
Projects Steering Committee
Dr. Abdullah S. Al-Qahtani
Approved2026-03-26