PRJ-2026-002Off track4ExecutionConstruction

SCA Headquarters, Riyadh

Remove from watchlist

A 210,000 m² campus in Al-Malqa housing the Authority’s offices, the contractors’ service hall and the conference & exhibition building in six linked buildings, with multi-storey parking.

Early warning: ⁦88%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 1.2B

Actual cost

SAR 532.9M

⁦45%⁩ of budget

Progress

⁦42%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 1.3B

SAR +88.8M

SPI · CPI

0.82Schedule performance index · 0.820.93Cost performance index · 0.93

Forecast finish

⁦2027-09-12⁩

74 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure25 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 January 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate3 March 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate13 September 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate25 March 2027Closure · Not startedClosure · Not started

Change request

The change, its impact analysis and the approval decision

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Change request

The change, its impact analysis and the approval decision

Form no.
SCA-PMO-F09
Template edition
3.1
Version
V2
Form date
⁦2026-03-02⁩
Hijri
13 Ramadan 1447 AH
ApprovedCR-2026-002Add a third basement level to the conference & exhibition building

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-002
Project
SCA Headquarters, Riyadh
Portfolio
Headquarters & Regional Centres Portfolio
Sector
Corporate Support Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Ahmed Y. Asiri

1The change

TitleAuto-filled
Add a third basement level to the conference & exhibition building
KindAuto-filled
Scope
Requested byAuto-filled
Eng. Ahmed Y. Asiri
Raised onAuto-filled
⁦2026-03-02⁩

Reason

An updated parking study expects a shortfall for visitors and staff once the conference & exhibition building opens and hosts the Future Projects Forum

Justification

Building it now costs about 60% less than a car-park building later, and eases congestion around HQ

2Impact analysis

Cost

SAR +38.5M

Schedule

+60 days

Risk

9 → 12

Benefits

+9%

Risk impact

Raises the chance of extension claims

Benefits impact

420 more parking spaces for visitors and staff

3The approval decision

The PMO’s recommendation

The PMO recommends approval with a fixed unit rate for the concrete works

Change Committee decision
Approve with conditions
Decided on
⁦2026-03-22⁩
Decision number
DEC-2026-009

Conditions

  • Fix the unit rate for concrete works

Approval logChain: Change request approval · version ⁦5⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Ahmed Y. AsiriDirector, Construction ProjectsSubmitted—⁦2026-03-02⁩ 11:26
2Project managerTechnical acceptanceEng. Ahmed Y. AsiriProject managerApproved—⁦2026-03-03⁩ 13:10
3PMO review & impact analysisMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-03-05⁩ 14:17
4Financial impactFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2026-03-09⁩ 12:45
5Contractual impactFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2026-03-10⁩ 13:22
6Change CommitteeTechnical acceptanceDr. Mohammed I. Al-SubaieChange CommitteeApproved—⁦2026-03-15⁩ 11:38
7Projects Steering CommitteeTechnical acceptanceApproval engineProjects Steering CommitteePre-breach alert—⁦2026-03-25⁩ 08:00
8Projects Steering CommitteeTechnical acceptanceDr. Abdullah S. Al-QahtaniProjects Steering CommitteeApproved—⁦2026-03-26⁩ 14:53

Signatures

Project manager

Eng. Ahmed Y. Asiri

Approved⁦2026-03-03⁩

PMO review & impact analysis

Ghada A. Al-Shahrani

Approved⁦2026-03-05⁩

Financial impact

Munirah A. Al-Khalidi

Approved⁦2026-03-09⁩

Contractual impact

Mazen A. Al-Hazmi

Approved⁦2026-03-10⁩

Change Committee

Dr. Mohammed I. Al-Subaie

Approved⁦2026-03-15⁩

Projects Steering Committee

Dr. Abdullah S. Al-Qahtani

Approved⁦2026-03-26⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F09 · version V2

Change request

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Change request approval · version ⁦5⁩

Submitted by Eng. Ahmed Y. Asiri on ⁦2026-03-02⁩

  1. Technical acceptance

    Project manager

    Eng. Ahmed Y. Asiri · Project manager

    Approved · ⁦2026-03-03⁩ at ⁦13:10⁩

  2. Methodology review

    PMO review & impact analysis

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-03-05⁩ at ⁦14:17⁩

  3. Financial approval

    Financial impact

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2026-03-09⁩ at ⁦12:45⁩

  4. Financial approval

    Contractual impact

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2026-03-10⁩ at ⁦13:22⁩

  5. Technical acceptance

    Change Committee

    Dr. Mohammed I. Al-Subaie · Change Committee

    Approved · ⁦2026-03-15⁩ at ⁦11:38⁩

  6. Technical acceptance

    Projects Steering Committee

    Dr. Abdullah S. Al-Qahtani · Projects Steering Committee

    On the path because: Cost impact above the Change Committee’s authority?From the authority matrix

    Approved · ⁦2026-03-26⁩ at ⁦14:53⁩

Steps that do not apply to this record

  • Executive Committee — the condition «Cost impact above the Steering Committee’s authority?» does not holdFrom the authority matrix

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2026-03-22⁩

    Approved by the committee

    • Fix the unit rate for concrete works

    Eng. Ahmed Y. Asiri

  2. V1Returned for edit⁦2026-03-02⁩

    The request as raised

    Eng. Ahmed Y. Asiri