SCA Systems Migration to the Cloud

Add to watchlist

Move 46 systems and applications to a licensed in-Kingdom cloud under the data classification framework and cloud controls.

Budget (BAC)

SAR 52M

Actual cost

SAR 25.2M

⁦48%⁩ of budget

Progress

⁦47%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 53.6M

SAR +1.6M

SPI · CPI

0.89Schedule performance index · 0.890.97Cost performance index · 0.97

Forecast finish

⁦2027-03-21⁩

21 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure8 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate11 September 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate8 January 2027Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−8

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is behind plan: ⁦47%⁩ done against ⁦53%⁩ planned.

SPI ⁦0.89⁩, CPI ⁦0.97⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: A Leading, Sustainable OrganisationSO-4.1Strong technical capabilities

Main initiative

SI-4.1.1Cloud & cybersecurity

Contribution to the initiative⁦22%⁩

The project’s share of the initiative’s project budget (3 projects)

Secondary links

No secondary links

Annual work-plan line
WP-2025-009
Classification
Operational

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦47%⁩

Awaiting acceptance ⁦12%⁩

Not handed in ⁦41%⁩

5 deliverables accepted

  • Release 1⁦16%⁩
  • Business requirements⁦11%⁩
  • Solution design⁦10%⁩
  • Project plan & baseline⁦5%⁩
  • Monitoring & reporting⁦5%⁩

1 deliverable under inspection or acceptance

  • Release 2⁦12%⁩

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦79%⁩ of budget

25.2M/ 52M1.6Mprojected overrun(⁦3.1%⁩)
Actual spend
25.2M
Committed
41M
Approved budget
52M
Estimate at completion
53.6M

Next milestones

  • Provisional acceptance⁦2027-01-24⁩was ⁦2027-01-08⁩At risk
  • Closure⁦2027-03-21⁩was ⁦2027-02-28⁩Late

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Change requests

Cost and schedule impact

  • No change requests

Risks & impediments

1 open risk, exposure SAR 2.6M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩1Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩RSK-0029Cloud consumption costs above estimateProbability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium1
  • Low0

Open impediments

⁦0⁩ escalated

  • No open impediments

Deliverables

⁦5⁩ of ⁦11⁩ approved

  • Project plan & baseline009-D1 · V1 · CRT-009-01⁦5%⁩Eng. Omar H. Bawazir⁦2025-08-28⁩2025-08-285 Rabiʻ I 1447 AHApproved
  • Monitoring & reporting009-D2 · V1 · CRT-009-02⁦5%⁩Eng. Nayef H. Al-Buqami⁦2025-10-22⁩2025-10-2230 Rabiʻ II 1447 AHApproved
  • Business requirements009-D3 · V1 · CRT-009-03⁦11%⁩Eng. Nayef H. Al-Buqami⁦2025-12-16⁩2025-12-1625 Jumada II 1447 AHApproved
  • Solution design009-D4 · V1 · CRT-009-04⁦10%⁩Eng. Majed S. Al-Rasheed⁦2026-02-09⁩2026-02-0921 Shaʻban 1447 AHApproved
  • Release 1009-D5 · V1 · CRT-009-05⁦16%⁩Eng. Majed S. Al-Rasheed⁦2026-04-05⁩2026-04-0517 Shawwal 1447 AHApproved
  • Release 2009-D6 · V1⁦12%⁩Eng. Omar H. Bawazir152 days overdue2026-05-2912 Dhuʻl-Hijjah 1447 AHIn review
  • Integrations009-D7 · V0⁦11%⁩Eng. Nayef H. Al-Buqami97 days overdue2026-07-239 Safar 1448 AHDraft
  • System testing009-D8 · V0⁦9%⁩Eng. Omar H. Bawazir42 days overdue2026-09-165 Rabiʻ II 1448 AHDraft
  • User acceptance testing009-D9 · V0⁦9%⁩Eng. Nayef H. Al-BuqamiIn 13 days2026-11-1030 Jumada I 1448 AHDraft
  • Training & change009-D10 · V0⁦6%⁩Eng. Nayef H. Al-BuqamiIn 68 days2027-01-0426 Rajab 1448 AHDraft
  • Go-live & handover009-D11 · V0⁦6%⁩Eng. Majed S. Al-RasheedIn 123 days2027-02-2821 Ramadan 1448 AHDraft

Team, contracts & documents

Team

3 members

Eng. Omar H. Bawazir · Director, IT InfrastructureEng. Nayef H. Al-Buqami · Director General, Information TechnologyEng. Saad M. Al-Dosari · Cloud & Integration Engineer
  • Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureProject managerP-024o.bawazir@sca.sa⁦40%⁩
  • Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyProject sponsorP-017n.albuqami@sca.sa⁦20%⁩
  • Eng. Saad M. Al-DosariEng. Saad M. Al-DosariCloud & Integration EngineerSCA systems migration to the cloudP-034sa.aldosari@sca.sa⁦30%⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close