SCA Systems Migration to the Cloud
Add to watchlistMove 46 systems and applications to a licensed in-Kingdom cloud under the data classification framework and cloud controls.
Budget (BAC)
Actual cost
48% of budget
Progress
Estimate at completion
SAR +1.6M
SPI · CPI
Forecast finish
21 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure8 January 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate11 September 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate8 January 2027Closure · Not startedClosure · Not started
Closure readiness
Closure planned after the forecast finish on 2027-03-21
A preview of what closure will need, with the planned dates, and the lessons captured so far.
Closure checklist
Seven mandatory items before any project closes.
- 1
Deliverables acceptedNot started
Final acceptance of every deliverable
Eng. Nayef H. Al-BuqamiPlanned 2027-03-11
- 2
Financial closureNot started
Spend reconciled, commitments closed
Khalid N. Al-MutairiPlanned 2027-04-10
- 3
Contract closureNot started
Contracts closed, retention released
Khalid N. Al-MutairiPlanned 2027-04-20
- 4
Documents archivedNot started
Documents archived with classification
Eng. Omar H. BawazirPlanned 2027-04-15
- 5
Lessons learnedNot started
Lessons-learned session
Eng. Omar H. BawazirPlanned 2027-04-05
- 6
Benefits owner assignedNot started
Benefits handed to their owner with a measurement plan
Eng. Nayef H. Al-BuqamiPlanned 2027-03-31
- 7
Final report approvedNot started
Final report and its approval
Eng. Omar H. BawazirPlanned 2027-04-25
Post-implementation review
Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?
The review comes after closure
About three months after the forecast finish (2027-03-21), with the sponsor and the benefits owner.
Lessons learned
0 lessons — offered automatically to similar projects when they are created.
No lessons captured yet
Capture what the team learned during delivery; closure needs at least one.
Benefits handover
Each benefit moves from the project manager to an owner who measures it after closure.
No benefits recorded for this project.