Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-030On track5ClosureWaterfall

Enterprise Risk & Business Continuity Framework

Add to watchlist

A framework, policies and a single register for enterprise risk and business continuity, with a risk appetite approved by the board.

Project managerTariq S. Al-YamiProject sponsorDr. Mohammed I. Al-Subaie

Budget (BAC)

SAR 3.6M

Actual cost

SAR 3.5M

⁦96%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 3.5M

SPI · CPI

1.00Schedule performance index · 1.001.04Cost performance index · 1.04

Forecast finish

⁦2026-08-31⁩

On baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate8 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate9 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate3 June 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate19 July 2026Closure · Current stageClosure · Current stage

Closing

⁦4⁩ of ⁦7⁩ closure items done

Finish the open items and hand the benefits to their owner, then close the project. No project closes without lessons learned.

4/7

Closure checklist

Seven mandatory items before any project closes.

  1. 1

    Deliverables acceptedDone

    Framework, policies and risk appetite approved by the SCA board

    Dr. Amal F. Al-SudairiDone ⁦2026-08-31⁩

  2. 2

    Financial closureIn progress

    Reconciling SAR ⁦3.46M⁩ spend; closing the last SAR ⁦40K⁩ of commitments

    Haifa S. Al-RuwailiPlanned ⁦2026-11-05⁩

  3. 3

    Contract closureDone

    No external contracts — delivered in-house

    Tariq S. Al-YamiDone ⁦2026-09-10⁩

  4. 4

    Documents archivedIn progress

    ⁦31⁩ of ⁦38⁩ documents archived

    Tariq S. Al-YamiPlanned ⁦2026-11-02⁩Evidence

  5. 5

    Lessons learnedDone

    One lesson published on sector risk champions

    Tariq S. Al-YamiDone ⁦2026-10-14⁩Evidence

  6. 6

    Benefits owner assignedNot started

    Hand the response-plan benefit from the PM to the Director General, Strategy & Performance

    Dr. Amal F. Al-SudairiPlanned ⁦2026-10-31⁩

    Hand over benefits ↓
  7. 7

    Final report approvedDone

    Closure report ⁦V1⁩ approved

    Tariq S. Al-YamiDone ⁦2026-10-14⁩Evidence

Post-implementation review

Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?

· Facilitated by Dr. Noura M. Al-Otaibi

Did it reach its goal?

Yes

100%

Every deliverable done; the board approved the risk appetite.

Did it stay on budget?

Yes

−3.9%

SAR ⁦3.46M⁩ against ⁦3.6M⁩, on time.

Were the benefits realised?

Partly

78%

⁦78%⁩ of risks have a response plan vs ⁦90%⁩ targeted at ⁦12⁩ months.

What did we learn?

Yes

1

One lesson published; a second proposed on linking the register to Munjaz.

What should improve?

Partly

—

To complete in the post-closure review session.

Lessons learned

1 lesson — offered automatically to similar projects when they are created.

Knowledge base
LL-035Stakeholderscited ⁦2⁩ times

Name a project champion in every sector from day one

Context
A risk and business-continuity framework needs every sector of the Authority involved.
What happened
Two sectors lagged until a named coordinator was set for each.
Impact
Risks with a response plan rose from ⁦35%⁩ to ⁦78%⁩.
Recommendation
Add a “sector champion” role to the communication-plan template.
Tariq S. Al-Yami · ⁦2026-09-28⁩

Benefits handover

Each benefit moves from the project manager to an owner who measures it after closure.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close