PRJ-2026-030On track5ClosureWaterfall
Enterprise Risk & Business Continuity Framework
Add to watchlistA framework, policies and a single register for enterprise risk and business continuity, with a risk appetite approved by the board.
Project managerTariq S. Al-YamiProject sponsorDr. Mohammed I. Al-Subaie
Budget (BAC)
SAR 3.6M
Actual cost
SAR 3.5M
96% of budget
Progress
100%Awaiting acceptance 0%
Estimate at completion
SAR 3.5M
SPI · CPI
1.00Schedule performance index · 1.001.04Cost performance index · 1.04
Forecast finish
2026-08-31
On baseline
ClosureStage 5 of 5
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate8 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate9 March 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate3 June 2025Execution · CompleteExecution · Complete
- Gate into «Closure»DecisionGoDate19 July 2026Closure · Current stageClosure · Current stage
Periodic update cards
Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.
Periodic update cards
No update cards for this project — they start with execution.