PRJ-2026-030On track5ClosureWaterfall

Enterprise Risk & Business Continuity Framework

Add to watchlist

A framework, policies and a single register for enterprise risk and business continuity, with a risk appetite approved by the board.

Project managerTariq S. Al-YamiProject sponsorDr. Mohammed I. Al-Subaie

Budget (BAC)

SAR 3.6M

Actual cost

SAR 3.5M

⁦96%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 3.5M

SPI · CPI

1.00Schedule performance index · 1.001.04Cost performance index · 1.04

Forecast finish

⁦2026-08-31⁩

On baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate8 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate9 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate3 June 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate19 July 2026Closure · Current stageClosure · Current stage

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 3.6M split into spent, committed and left, with the estimate at completion

EAC SAR 3.5M
Revised request SAR 3.6M
  • Actual spendSAR 3.5M
  • Committed, not spentSAR 38K
  • Allotted, uncommittedSAR 0
  • Contingency availableSAR 108K

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 3.3M
Original budgetwhen the first baseline was approved
SAR 3.6M
Approved budgetafter approved change requests
SAR 3.6M
Current budgetavailable to spend now
SAR 3.6M
Revised budgetif the pending changes are approved
SAR 3.6M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 3.5M
Contracts0 active contracts
SAR 0
Purchase orders⁦2⁩ orders
SAR 3.5M
Remaining budgetapproved less actual
SAR 138K

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 3.5M
Accrualswork done, not yet invoiced
SAR 138K
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 3.5M
ContingencySAR 72K drawn of SAR 180K
SAR 108K

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 3.3M
ApprovedSAR 3.6M
Estimate at completionSAR 3.5M
Approved is SAR 300K (⁦9.1%⁩) above the estimate
The estimate at completion is SAR 162K (⁦4.9%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2024-12-24⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-21030
  • WBS elements⁦5⁩ elements · P-2026-030.01 …
  • Purchase orders⁦2⁩ synced · ⁦0⁩ manual
  • Invoices & certificatesNo certificates
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 72K drawn of SAR 180K

  • Covering realised delivery risks⁦2026-08-29⁩SAR 72K

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance0.350.350.350.34⁦+0.01⁩
2Diagnosis0.700.700.690.68⁦+0.02⁩
3Design1.051.051.041.02⁦+0.03⁩
4Implementation1.051.051.041.02⁦+0.03⁩
5Handover & knowledge transfer0.350.350.350.34⁦+0.01⁩
Unallocated contingency0.110.000.000.05⁦+0.05⁩
Total3.603.503.463.46⁦+0.14⁩

Budget split

WBS

SAR 3.6M

Budget

  • Management & governanceSAR 349.2K⁦10%⁩
  • DiagnosisSAR 698.4K⁦19%⁩
  • DesignSAR 1M⁦29%⁩
  • ImplementationSAR 1M⁦29%⁩
  • Handover & knowledge transferSAR 349.2K⁦10%⁩
  • Unallocated contingencySAR 108K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2026-08-31⁩

SPI(t) ⁦1.00⁩ against the approved finish ⁦2026-08-31⁩

Planned valuePV
SAR 3.6M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 3.6M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 3.5M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 3.6M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.14⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦+0.00⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.04
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
1.00
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 3.5M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 0
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.14⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
0.00
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 3.5M
  • If the rest goes to planSAR 3.5M
  • At cost and schedule performanceSAR 3.5M
  • The PM’s bottom-up estimateSAR 3.5M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SAR 3.5M

Variance at completion: ⁦+0.14⁩ SAR M