Original
Original baseline
- Finish
- 2026-08-31
- Budget
- SAR 3.6M
- 15 activities
Approved with the project plan at the planning gate.
Approved 2025-03-09 · by Dr. Mohammed I. Al-Subaie
A framework, policies and a single register for enterprise risk and business continuity, with a risk appetite approved by the board.
Budget (BAC)
Actual cost
96% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ClosureStage 5 of 5
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2025-03-09 · by Dr. Mohammed I. Al-Subaie
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Tariq S. Al-Yami
What changed from version A to version B
Finish
2026-08-312026-10-26
+56 days
Budget
SAR 3.6MSAR 3.6M
0.00 SAR M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SAR millions from A to B
Every saved version with its reason and reference