Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-030On track5ClosureWaterfall

Enterprise Risk & Business Continuity Framework

Add to watchlist

A framework, policies and a single register for enterprise risk and business continuity, with a risk appetite approved by the board.

Project managerTariq S. Al-YamiProject sponsorDr. Mohammed I. Al-Subaie

Budget (BAC)

SAR 3.6M

Actual cost

SAR 3.5M

⁦96%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 3.5M

SPI · CPI

1.00Schedule performance index · 1.001.04Cost performance index · 1.04

Forecast finish

⁦2026-08-31⁩

On baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate8 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate9 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate3 June 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate19 July 2026Closure · Current stageClosure · Current stage

Project closure & handover

Performance, handover, open commitments and lessons learned

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Closure

Project closure & handover

Performance, handover, open commitments and lessons learned

Form no.
SCA-PMO-F12
Template edition
2.0
Version
V1
Form date
⁦2026-10-12⁩
Hijri
1 Jumada I 1448 AH
In approvalPRJ-2026-030Enterprise Risk & Business Continuity Framework

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-030
Project
Enterprise Risk & Business Continuity Framework
Portfolio
Institutional Excellence & Governance Portfolio
Sector
Strategy & Institutional Excellence Sector
Sponsor
Dr. Mohammed I. Al-Subaie
Project manager
Tariq S. Al-Yami

1PerformanceAuto-filled

Approved budget

SAR 3.6M

Actual cost

SAR 3.5M

Cost variance

SAR +138K

Schedule variance

0 days

Post-implementation questionVerdictAnswer
Did the project meet its goal?YesEvery deliverable done; the board approved the risk appetite.
Was it delivered within budget?YesSAR 3.46M against 3.6M, on time.
Are the benefits showing?Partly78% of risks have a response plan vs 90% targeted at 12 months.
Were the lessons captured?YesOne lesson published; a second proposed on linking the register to Munjaz.
What to improve next time?PartlyTo complete in the post-closure review session.

2HandoverAuto-filled

ItemStateOwnerEvidence
Final acceptance of deliverablesDoneDr. Amal F. Al-SudairiFramework, policies and risk appetite approved by the SCA board
Financial settlementIn progressHaifa S. Al-RuwailiReconciling SAR 3.46M spend; closing the last SAR 40K of commitments
Contracts closedDoneTariq S. Al-YamiNo external contracts — delivered in-house
Documents archivedIn progressTariq S. Al-Yami31 of 38 documents archived
Lessons learnedDoneTariq S. Al-YamiOne lesson published on sector risk champions
Benefits handed to their ownerOpenDr. Amal F. Al-SudairiHand the response-plan benefit from the PM to the Director General, Strategy & Performance
Final reportDoneTariq S. Al-YamiClosure report V1 approved
BenefitNew ownerHandover
Enterprise risks with a response and continuity planDr. Amal F. Al-SudairiPending

3Open commitments

CommitmentOwnerDue
Financial settlement — Reconciling SAR 3.46M spend; closing the last SAR 40K of commitmentsHaifa S. Al-Ruwaili⁦2026-11-05⁩
Documents archived — 31 of 38 documents archivedTariq S. Al-Yami⁦2026-11-02⁩
Benefits handed to their owner — Hand the response-plan benefit from the PM to the Director General, Strategy & PerformanceDr. Amal F. Al-Sudairi⁦2026-10-31⁩

4Lessons learnedAuto-filled

  1. Name a project champion in every sector from day one

Approval logChain: Project closure & handover approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Tariq S. Al-YamiHead, Performance & RiskSubmitted—⁦2026-10-12⁩ 11:56
2Closure file completenessMethodology reviewApproval enginePMO — analystPre-breach alert—⁦2026-10-15⁩ 08:00
3Closure file completenessMethodology reviewApproval engineEscalated automatically to PMO — director (Dr. Noura M. Al-Otaibi) on ⁦2026-10-19⁩Automatic escalation—⁦2026-10-19⁩ 08:05

Signatures

Closure file completeness

Ghada A. Al-Shahrani

Awaiting decision

Handover accepted — project owner

Dr. Amal F. Al-Sudairi

Later

Final financial settlement

Munirah A. Al-Khalidi

Later

Project Approval Committee

Dr. Noura M. Al-Otaibi

Later

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F12 · version V1

Project closure & handover

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project closure & handover approval · version ⁦1⁩

Submitted by Tariq S. Al-Yami on ⁦2026-10-12⁩

  1. Methodology review

    Closure file completeness

    Ghada A. Al-Shahrani · PMO — analyst

    Delegated to Dr. Noura M. Al-Otaibi

    9 working days overdueAction time limit exceeded · Limit 3 working daysLimit 3 working days · Due ⁦2026-10-15⁩

    Pre-breach alert at ⁦75%⁩ — sent ⁦2026-10-15⁩

    Escalated automatically to PMO — director (Dr. Noura M. Al-Otaibi) on ⁦2026-10-19⁩

  2. Technical acceptance

    Handover accepted — project owner

    Dr. Amal F. Al-Sudairi · Project owner

    Limit 3 working days · Expected by ⁦2026-10-20⁩

  3. Financial approval

    Final financial settlement

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Delegated to Khalid N. Al-Mutairi

    Limit 3 working days · Expected by ⁦2026-10-25⁩

  4. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Limit 5 working days · Expected by ⁦2026-11-01⁩

Steps that do not apply to this record

  • Contracts closed, guarantees released — the condition «Contract link?» does not hold

Previous versions

Every version is kept with its status and what changed.

  1. V1In approvalCurrent⁦2026-10-12⁩

    The closure file in preparation

    Tariq S. Al-Yami

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close