PRJ-2026-031On track5ClosureScrum

Electronic Model Contracts

Add to watchlist

Draft, sign and register model contracting agreements online, with both parties alerted to obligations and dates.

Budget (BAC)

SAR 8.2M

Actual cost

SAR 8M

⁦97%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 8M

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage

Closed project

Project closed on ⁦2025-09-28⁩

All seven closure items are done, the post-implementation review was held, and the benefits passed to their owner to measure.

7/7

Closure checklist

Seven mandatory items before any project closes.

  1. 1

    Deliverables acceptedDone

    Final acceptance of ⁦9⁩ deliverables, no open findings

    Faisal A. Al-ShehriDone ⁦2025-07-20⁩

  2. 2

    Financial closureDone

    Actual SAR ⁦7.96M⁩ of ⁦8.2M⁩ — SAR ⁦240K⁩ returned to budget

    Khalid N. Al-MutairiDone ⁦2025-09-10⁩

  3. 3

    Contract closureDone

    Contract ⁦SCA/2024/009⁩ closed, retention released

    Khalid N. Al-MutairiDone ⁦2025-09-14⁩Evidence

  4. 4

    Documents archivedDone

    ⁦64⁩ documents archived with their classification

    Karim HaddadDone ⁦2025-09-18⁩Evidence

  5. 5

    Lessons learnedDone

    ⁦3⁩ lessons published, cited ⁦13⁩ times since

    Karim HaddadDone ⁦2025-08-30⁩Evidence

  6. 6

    Benefits owner assignedDone

    Eng. Reem Al-Dosari owns two benefits with a ⁦24-month⁩ plan

    Eng. Reem K. Al-DosariDone ⁦2025-09-21⁩

  7. 7

    Final report approvedDone

    Final report approved by the sponsor and the PMO

    Karim HaddadDone ⁦2025-09-28⁩

Post-implementation review

Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?

Held on ⁦2025-10-22⁩Review score 84/100· Facilitated by Dr. Noura M. Al-Otaibi

Did it reach its goal?

Yes

9/9

Yes. Electronic model contracts went live with nine models; over ⁦41K⁩ contracting agreements registered on them in year one.

Did it stay on budget?

Yes

−2.9%

Delivered for SAR ⁦7.96M⁩ against ⁦8.2M⁩, ⁦20⁩ days after baseline.

Were the benefits realised?

Partly

82%

⁦82%⁩ realised: satisfaction ⁦82%⁩ vs ⁦85%⁩ target, ⁦18⁩ minutes to sign a contract vs ⁦15⁩.

What did we learn?

Yes

3

Three lessons: Nafath environments, payments tied to acceptance, the vendor team.

What should improve?

Partly

2

An SMS alert before contractual due dates, and linking each contract to the company file in Muqawil.

Lessons learned

2 lessons — offered automatically to similar projects when they are created.

LL-041Integrationcited ⁦6⁩ times

Book Nafath test environments three months before build

Context
Electronic model contracts needed Nafath single sign-on for both parties.
What happened
The test environment arrived seven weeks late because it was requested after build started.
Impact
Launch slipped five weeks; SAR ⁦340K⁩ extra vendor time.
Recommendation
Request the environment when the charter is approved and make it a planning-gate item.
Karim Haddad · ⁦2025-08-20⁩
LL-021Financecited ⁦3⁩ times

Tie payments to accepted deliverables, not elapsed time

Context
The electronic model contracts build contract.
What happened
A ⁦20%⁩ payment was released before the stage passed acceptance.
Impact
Hard to hold the vendor to ⁦37⁩ open defects.
Recommendation
A payment schedule tied to deliverable acceptance in every digital contract.
Khalid N. Al-Mutairi · ⁦2025-08-30⁩

Benefits handover

Each benefit moves from the project manager to an owner who measures it after closure.