PRJ-2026-031On track5ClosureScrum

Electronic Model Contracts

Add to watchlist

Draft, sign and register model contracting agreements online, with both parties alerted to obligations and dates.

Budget (BAC)

SAR 8.2M

Actual cost

SAR 8M

⁦97%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 8M

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage
Fields required by the project’s stage (Closure): 15 fields required now.Field settings

Saudi Contractors Authority

Project charter

Electronic Model Contracts

APPROVEDV2Approved ⁦2024-04-05⁩

1Project identity

Required at this stage
Project name
Electronic Model Contracts
Project code
PRJ-2026-031
Project sponsor
Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.sa
Project manager
Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@sca.sa
Project owner
Faisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio ManagerP-003f.alshehri@sca.sa
Portfolio & programme
Digital Services & Platforms PortfolioMuqawil & e-Services Programme
Type & methodology
Digital · Scrum
Current phase
5Closure

2Background & rationale

Required at this stage

Draft, sign and register model contracting agreements online, with both parties alerted to obligations and dates.

3Objectives

Required at this stage
  1. 1Simplify regulatory relationships and make doing business easier

4Scope

Required at this stage

In scope

  • Draft, sign and register model contracting agreements online, with both parties alerted to obligations and dates.
  • Single sign-on through Nafath
  • Integration with internal systems

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Single sign-on through Nafath
  2. 2Integration with internal systems
  3. 3Digital Government Authority standards

6Deliverables

Required at this stage
1Project management plan⁦2024-04-25⁩
2Main deliverable — stage 1⁦2024-11-22⁩
3Main deliverable — final stage⁦2025-04-28⁩
4Final report⁦2025-06-30⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2024-04-05⁩
  2. Contract signed⁦2024-06-18⁩
  3. 50% of works complete⁦2024-11-22⁩
  4. Provisional acceptance⁦2025-05-25⁩
  5. Closure⁦2025-06-30⁩

8Budget

Required at this stage
  • Main contract⁦72.0%⁩5.9M
  • Supervision & consulting⁦14.6%⁩1.2M
  • Internal team⁦8.5%⁩700K
  • Contingency reserve (⁦5%⁩)⁦4.9%⁩400K
The owning sector’s approved budgetTotal8.2M

9Timeline

Required at this stage
Start
2024-04-0728 Ramadan 1445 AH
Baseline finish
2025-06-305 Muharram 1447 AH
Duration
⁦15⁩ months

10Key risks

Required at this stage
  • No risks recorded yet.

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3Target benefits within ⁦12⁩ months

15Governance structure

Required at this stage
  • Change Control BoardApproves scope, cost and schedule changesWeekly
  • PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Board