PRJ-2026-031On track5ClosureScrum

Electronic Model Contracts

Add to watchlist

Draft, sign and register model contracting agreements online, with both parties alerted to obligations and dates.

Budget (BAC)

SAR 8.2M

Actual cost

SAR 8M

⁦97%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 8M

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage

Team & roles

1 member, about ⁦0.0⁩ full-time equivalents

Leadership

1 member

  • Karim HaddadProject manager⁦0%⁩A

A AccountableR ResponsibleC ConsultedI Informed

Stakeholders

⁦6⁩ stakeholders, ⁦3⁩ of them below the engagement needed

Power / interest matrix

Pick one to see how they are handled

Power & influence

Keep satisfied1

high power, lower interest

Manage closely4

high power and interest

Monitor0

minimal effort

Keep informed1

high interest, lower power

Eng. Majed S. Al-RasheedManage closelyFaisal A. Al-ShehriManage closelyProject Management Office (PMO)Manage closelyEnd beneficiariesKeep informedGeneral Directorate of Financial AffairsKeep satisfiedDigital Platforms Solutions Co.Manage closely

Interest

Project sponsor

Eng. Majed S. Al-Rasheed

Decisions and funding

Influence

Interest

Engagement level

Unaware

Resistant

Neutral

Now

Supportive

Target

Leading

A gap of ⁦1⁩ step — needs an engagement plan.

Impact on the project
Approves gates and changes
Engagement plan
Monthly briefing
Last contact⁦2026-09-29⁩
⁦6⁩ results
Export CSV
OrganisationRoleActions
Eng. Majed S. Al-RasheedProject sponsorDecisions and fundingSupportiveLeadingKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@sca.sa⁦2026-09-29⁩
Faisal A. Al-ShehriProject ownerAccepts deliverables, owns benefitsLeadingKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@sca.sa⁦2026-10-02⁩
Project Management Office (PMO)GovernanceCompliance and data qualitySupportiveKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@sca.sa⁦2026-09-26⁩
General Directorate of Financial AffairsInternal departmentPayment approvalNeutralSupportiveHaifa S. Al-RuwailiHaifa S. Al-RuwailiSenior Financial AnalystP-037h.alruwaili@sca.sa⁦2026-09-23⁩
Digital Platforms Solutions Co.Main vendorDelivers the contracted workLeadingKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@sca.sa⁦2026-10-03⁩
End beneficiariesBeneficiariesUsers of the outcomeNeutralSupportiveKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@sca.sa⁦2026-09-05⁩
⁦1⁩–⁦6⁩ of ⁦6⁩

Communication plan

Who needs what, when, through which channel, and who owns it.

  • Project sponsorStatus and decisions neededMonthlyMeetingKarim Haddad⁦2026-10-25⁩
  • Project ownerDeliverable status and acceptance datesFortnightlyEmailKarim Haddad⁦2026-10-13⁩Overdue
  • PMOData and indicator updatesWeeklyDashboardKarim Haddad⁦2026-10-10⁩
  • BeneficiariesWhat changes and whenAt milestonesNewsletterKarim HaddadAt launch

Coming up

By date

  1. 102026-10PMODashboard · Weekly
  2. 132026-10Project ownerEmail · Fortnightly
  3. 252026-10Project sponsorMeeting · Monthly