Late Nafath and Government Service Bus readiness delays both Muqawil and the app
PRK-01-1·Mitigate·Eng. Reem K. Al-Dosari
Programme · PG-01 · Digital Services & Platforms Portfolio
One contractor journey across Muqawil, the app, Wifaq and the electronic model contracts.
incl. SAR 4M programme reserve
65% of budget
Estimate at completion
Planned 78%
Cost performance index 0.98
Manager
Eng. Reem K. Al-Dosari
Head of the Muqawil Platform & Programme Manager, Muqawil & e-Services
Sponsor
Eng. Majed S. Al-Rasheed
Head, Digital Transformation Sector
Projects
4 projects
2024-04-07 — 2027-05-12
On track 3At risk 1
What the programme must achieve, and the strategic objectives it serves.
One contractor journey for every SCA service on Muqawil and the app, signed in with Nafath
Lift SCA services fully available online from 55% to 80% by the end of 2027
Cut in-person visits to the contractor service centres by 40% by moving them to digital channels
From baseline to target
Contractor satisfaction with digital services
by 2027Average time to issue or renew membership
by 2027Running savings at the contractor service centres
by 2028One lane per project: start to forecast finish, with the progress earned and the baseline finish.
What waits on what. Red links are on the programme’s critical path.
Critical path
The model-contracts engine is reused inside Muqawil for the service centres
Settlement records in Wifaq are linked to the membership file in Muqawil after launch
Critical
The mobile app consumes Muqawil’s APIs and the Nafath integration
Risks that hit more than one project, managed at programme level.
Late Nafath and Government Service Bus readiness delays both Muqawil and the app
PRK-01-1·Mitigate·Eng. Reem K. Al-Dosari
One vendor integration team serves three projects in the programme
PRK-01-2·Escalate·Eng. Reem K. Al-Dosari
10 risks
Impact
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 0 · Low | 0 · Medium | 0 · High | 0 · Critical | 0 · Critical |
| 4 | 0 · Low | 0 · Medium | 0 · Medium | 2 · High | 0 · Critical |
| 3 | 0 · Low | 0 · Low | 3 · Medium | 2 · Medium | 0 · High |
| 2 | 0 · Low | 0 · Low | 2 · Low | 1 · Medium | 0 · Medium |
| 1 | 0 · Low | 0 · Low | 0 · Low | 0 · Low | 0 · Low |
Membership and renewal requests completed with no visit
58%
+1
Target 60%97%
Average time to issue a technical-standards certificate
9.5days
−1
Target 7.0
Contractor satisfaction with digital services
74%
0
Target 85%87%
Accredited qualification programmes and professional tracks
37programmes
+4
Target 4093%
Power against interest; click a person to see their role.
Keep satisfied2
Manage closely3
Monitor0
Keep informed1
Interest
What the committees decided on the programme’s projects, and what the programme raised to them.
Committees
Monthly · Quorum 5
Members
6 members
Fortnightly · Quorum 4
Members
7 members
Weekly · Quorum 4
Members
5 members
The programme’s performance is computed from these projects.
Display options
| Manager | ||||||||
|---|---|---|---|---|---|---|---|---|
| Wifaq Dispute Settlement Platform — Release 2PRJ-2026-008 | Karim Haddad | 4Execution | On track | 91% | 18.4M | 18M−2.0% | 1.01Schedule performance index · 1.01 | 1.02Cost performance index · 1.02 |
| Muqawil Platform — Release 4PRJ-2026-014 | Eng. Sultan F. Al-Ghamdi | 4Execution | At risk | 58% | 86.4M | 90M+4.2% | 0.87Schedule performance index · 0.87 | 0.96Cost performance index · 0.96 |
| Muqawil Mobile App — Release 3PRJ-2026-015 | Karim Haddad | 4Execution | On track | 64% | 12.6M | 12.1M−3.8% | 1.02Schedule performance index · 1.02 | 1.04Cost performance index · 1.04 |
| Electronic Model ContractsPRJ-2026-031 | Karim Haddad | 5Closure | On track | 100% | 8.2M | 8M−2.9% | 1.00Schedule performance index · 1.00 | 1.03Cost performance index · 1.03 |
| Total · 4 | 125.6M | 128.1M |
SAR 125.6M
Budget
| Category | Value | Share |
|---|---|---|
| Wifaq Dispute Settlement Platform — Release 2 | SAR 18.4M | 15% |
| Muqawil Platform — Release 4 | SAR 86.4M | 69% |
| Muqawil Mobile App — Release 3 | SAR 12.6M | 10% |
| Electronic Model Contracts | SAR 8.2M | 7% |
| Total | SAR 125.6M | 100% |