PRJ-2026-031On track5ClosureScrum

Electronic Model Contracts

Add to watchlist

Draft, sign and register model contracting agreements online, with both parties alerted to obligations and dates.

Budget (BAC)

SAR 8.2M

Actual cost

SAR 8M

⁦97%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 8M

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage

Scope statementRequired at this stage

What the project delivers, what it does not, and when a deliverable counts as accepted.

Draft, sign and register model contracting agreements online, with both parties alerted to obligations and dates.

In scope

  • Draft, sign and register model contracting agreements online, with both parties alerted to obligations and dates.
  • Single sign-on through Nafath
  • Integration with internal systems

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

Acceptance criteria

  • Main deliverable — stage 1Meets the approved specification, signed off by the project owner
  • Main deliverable — final stageMeets the approved specification, signed off by the project owner

Scope baselineRequired at this stage

Every approved change creates a new baseline

  1. 1

    SB-1Current⁦2024-04-29⁩

    Baseline approved at the planning gate

    Budget8.2MFinish⁦2025-06-30⁩

Requirements registerRequired at this stage

⁦6⁩ requirements of five kinds, with the trace status of each

By type

  • Business1
  • Functional2
  • Technical1
  • Regulatory1
  • Security1

Fully traced

⁦100%⁩

6/6 · linked to a deliverable, task and test

Test passed

⁦100%⁩

6/6 · test result is a pass

Accepted

⁦100%⁩

6/6 · signed off by the business owner

⁦6⁩ results
Export CSV
REQ-031-01An end-to-end digital journey, no walk-inBusinessMustCompletedFaisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio ManagerP-003f.alshehri@sca.saSB-1
REQ-031-02Nafath single sign-onFunctionalMustCompletedKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@sca.saSB-1
REQ-031-03A user dashboardFunctionalMustCompletedFaisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio ManagerP-003f.alshehri@sca.saSB-1
REQ-031-04Integration with internal systemsTechnicalShouldCompletedKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@sca.saSB-1
REQ-031-05WCAG ⁦2.1⁩ accessibilityRegulatoryShouldCompletedFaisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio ManagerP-003f.alshehri@sca.saSB-1
REQ-031-06Essential cybersecurity controlsSecurityCouldCompletedKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@sca.saSB-1
⁦1⁩–⁦6⁩ of ⁦6⁩

Traceability matrixRequired at this stage

Requirement → deliverable → task → test → acceptance. No requirement has a gap.