Electronic Model Contracts
Add to watchlistDraft, sign and register model contracting agreements online, with both parties alerted to obligations and dates.
Budget (BAC)
Actual cost
97% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
20 days behind baseline
ClosureStage 5 of 5
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
- Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage