PRJ-2026-031On track5ClosureScrum

Electronic Model Contracts

Add to watchlist

Draft, sign and register model contracting agreements online, with both parties alerted to obligations and dates.

Budget (BAC)

SAR 8.2M

Actual cost

SAR 8M

⁦97%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 8M

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage

Project documents by stage

What each stage requires under the RFP, what has been filed and what is missing, and the evidence tied to deliverables.

  • ⁦7⁩ of ⁦9⁩ mandatory documents due
  • 2 mandatory documents missing
  • 7 documents in the repository

A closed project — documents archived

Every project document moved to «Archive» when it closed, read-only under the retention policy.

Stages and required documents

For each of the five stages, what its gates and forms require: present, missing, or not yet due.

  1. 1Pre-start
  2. 2Initiation
  3. 3Planning
    • Project management plan, schedule & baselineMandatory· Present

      Project management plan & baseline — model contractsV1

      Planning gate G3

    • Contract or purchase orderMandatory· Missing

      Finance & procurement — when there is a contract

    • Technical studies & drawingsOptional· Missing

      Project management plan

  4. 4Execution
  5. 5Closure

Evidence tied to deliverables

Each deliverable with its repository document and the files that prove it.

  • 031-D1Project plan & baselinePRJ-2026-031_1.1_v1.pdfApprovedDeliverable
  • 031-D2Monitoring & reportingPRJ-2026-031_1.2_v1.pdfApprovedDeliverable
  • 031-D3Business requirementsPRJ-2026-031_2.1_v1.pdfApprovedDeliverable
  • 031-D4Solution designPRJ-2026-031_2.2_v1.pdfApprovedDeliverable
  • 031-D5Release 1PRJ-2026-031_3.1_v1.pdfApprovedDeliverable
  • 031-D6Release 2PRJ-2026-031_3.2_v1.pdfApprovedDeliverable
  • 031-D7IntegrationsPRJ-2026-031_3.3_v1.pdfApprovedDeliverable
  • 031-D8System testingPRJ-2026-031_4.1_v1.pdfApprovedDeliverable
  • 031-D9User acceptance testingPRJ-2026-031_4.2_v1.pdfApprovedDeliverable
  • 031-D10Training & changePRJ-2026-031_5.1_v1.pdfApprovedDeliverable
  • 031-D11Go-live & handoverPRJ-2026-031_5.2_v1.pdfApprovedDeliverable