Deliverable completion certificate — drafting & signing platform

InternalApprovedV1

Deliverable completion certificate — drafting & signing platform

More

Internal

Kingdom of Saudi Arabia

Saudi Contractors Authority

Project Management Office (PMO)

Code
DOC-0305
Version
V1
Date
2025-06-22

Deliverable completion certificate — drafting & signing platform

Electronic Model Contracts

⁦1⁩. Executive summary

This report gives the position of Electronic Model Contracts to date: ⁦100%⁩ complete against ⁦100%⁩ planned, SPI ⁦1.00⁩, CPI ⁦1.03⁩, and an estimate at completion of SAR ⁦8.0M⁩.

Project
Electronic Model Contracts (⁦PRJ-2026-031⁩)
Project manager
Karim Haddad
Budget
SAR ⁦8.2M⁩
Progress
⁦100%⁩ actual against ⁦100%⁩ planned
Forecast finish
⁦2025-07-20⁩

⁦2⁩. Key findings

  • All planned milestones of the period met except one deferred
  • Actual spend rose in line with the work done
  • Three high risks under treatment, each with a named owner

⁦3⁩. Recommendations & decisions needed

  • Approve the proposed treatment of the high risks
  • Track the open findings with the vendor weekly

Prepared by

Hala F. Al-Angari

Project manager

Karim Haddad
Issued from Munjaz — valid only once approved electronically1 / 1