PRJ-2026-031On track5ClosureScrum

Electronic Model Contracts

Add to watchlist

Draft, sign and register model contracting agreements online, with both parties alerted to obligations and dates.

Budget (BAC)

SAR 8.2M

Actual cost

SAR 8M

⁦97%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 8M

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2025-06-30⁩
    Budget
    SAR 8.2M
    ⁦16⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2024-04-07⁩ · by Eng. Majed S. Al-Rasheed

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2025-07-20⁩
    ⁦+20⁩ days
    Budget
    SAR 8.2M
    ⁦16⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Karim Haddad

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2025-06-30⁩⁦2025-07-20⁩

⁦+20⁩ days

Budget

SAR 8.2MSAR 8.2M

⁦0.00⁩ SAR M

Milestones moved

5 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2024-072025-012025-07
  • Project plan approved⁦+4⁩
  • Designs approved⁦+8⁩
  • Build complete⁦+13⁩
  • Testing & acceptance complete⁦+16⁩
  • Final handover⁦+20⁩

Version AVersion B

Cost by WBS element

Difference in SAR millions from A to B

  • 1Management & governance⁦−0.02⁩
  • 2Analysis & design⁦−0.02⁩
  • 3Build⁦+0.14⁩
  • 4Testing & acceptance⁦−0.02⁩
  • 5Launch & handover⁦−0.02⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Karim Haddad