PRJ-2026-031On track5ClosureScrum

Electronic Model Contracts

Add to watchlist

Draft, sign and register model contracting agreements online, with both parties alerted to obligations and dates.

Budget (BAC)

SAR 8.2M

Actual cost

SAR 8M

⁦97%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 8M

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

5Achieved
0On track
0At risk
0Late
Average delay12 days
Jul 24Oct 24Jan 25Apr 25Jul 25
Contractual
Build completePlanned: ⁦2025-01-26⁩Forecast / actual: ⁦2025-02-08⁩Delay: 13 daysG3 +13
Executive
Project plan approvedPlanned: ⁦2024-07-17⁩Forecast / actual: ⁦2024-07-21⁩Delay: 4 daysG1 +4
Payment
Final handoverPlanned: ⁦2025-06-30⁩Forecast / actual: ⁦2025-07-20⁩Delay: 20 daysG5 +20
Regulatory
Testing & acceptance completePlanned: ⁦2025-04-14⁩Forecast / actual: ⁦2025-04-30⁩Delay: 16 daysG4 +16
Project
Designs approvedPlanned: ⁦2024-10-02⁩Forecast / actual: ⁦2024-10-10⁩Delay: 8 daysG2 +8

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2024-07-17⁩⁦2024-07-21⁩⁦+4⁩ daysKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@sca.saAchieved1Approved
Designs approvedMS-G2Project⁦2024-10-02⁩⁦2024-10-10⁩⁦+8⁩ daysKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@sca.saAchieved1Approved
Build completeMS-G3Contractual⁦2025-01-26⁩⁦2025-02-08⁩⁦+13⁩ daysKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@sca.saAchieved1Approved
Testing & acceptance completeMS-G4Regulatory⁦2025-04-14⁩⁦2025-04-30⁩⁦+16⁩ daysKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@sca.saAchieved1Approved
Final handoverMS-G5Payment⁦2025-06-30⁩⁦2025-07-20⁩⁦+20⁩ daysKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@sca.saAchieved1Approved
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦100%⁩

Awaiting acceptance

⁦0%⁩

Not handed in

⁦0%⁩

Deliverable flow

Pick a stage to filter the register
⁦11⁩ results
Export CSV
Project plan & baseline031-D1⁦4%⁩CRT-031-01ApprovedKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@sca.saFaisal A. Al-Shehri⁦2024-06-08⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting031-D2⁦4%⁩CRT-031-02ApprovedFaisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio ManagerP-003f.alshehri@sca.saFaisal A. Al-Shehri⁦2024-07-17⁩V1⁦3⁩ of ⁦3⁩
Business requirements031-D3⁦9%⁩CRT-031-03ApprovedFaisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio ManagerP-003f.alshehri@sca.saFaisal A. Al-Shehri⁦2024-08-24⁩V1⁦3⁩ of ⁦3⁩
Solution design031-D4⁦9%⁩CRT-031-04ApprovedEng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.saFaisal A. Al-Shehri⁦2024-10-02⁩V1⁦3⁩ of ⁦3⁩
Release 1031-D5⁦13%⁩CRT-031-05ApprovedEng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.saFaisal A. Al-Shehri⁦2024-11-10⁩V1⁦3⁩ of ⁦3⁩
Release 2031-D6⁦13%⁩CRT-031-06ApprovedKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@sca.saFaisal A. Al-Shehri⁦2024-12-18⁩V1⁦3⁩ of ⁦3⁩
Integrations031-D7⁦13%⁩CRT-031-07ApprovedFaisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio ManagerP-003f.alshehri@sca.saFaisal A. Al-Shehri⁦2025-01-26⁩V1⁦3⁩ of ⁦3⁩
System testing031-D8⁦10%⁩CRT-031-08ApprovedKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@sca.saFaisal A. Al-Shehri⁦2025-03-06⁩V1⁦3⁩ of ⁦3⁩
User acceptance testing031-D9⁦10%⁩CRT-031-09ApprovedFaisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio ManagerP-003f.alshehri@sca.saFaisal A. Al-Shehri⁦2025-04-14⁩V1⁦3⁩ of ⁦3⁩
Training & change031-D10⁦8%⁩CRT-031-10ApprovedFaisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio ManagerP-003f.alshehri@sca.saFaisal A. Al-Shehri⁦2025-05-22⁩V1⁦3⁩ of ⁦3⁩
Go-live & handover031-D11⁦7%⁩CRT-031-11ApprovedEng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.saFaisal A. Al-Shehri⁦2025-06-30⁩V1⁦3⁩ of ⁦3⁩
Total · 11⁦100%⁩
⁦1⁩–⁦11⁩ of ⁦11⁩