Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-031On track5ClosureScrum

Electronic Model Contracts

Add to watchlist

Draft, sign and register model contracting agreements online, with both parties alerted to obligations and dates.

Budget (BAC)

SAR 8.2M

Actual cost

SAR 8M

⁦97%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 8M

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
SCA-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2024-08-31⁩
Hijri
27 Safar 1446 AH
ApprovedCRT-031-03Business requirements

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-031
Project
Electronic Model Contracts
Portfolio
Digital Services & Platforms Portfolio
Sector
Regulation & Development Sector
Sponsor
Eng. Majed S. Al-Rasheed
Project manager
Karim Haddad

1The deliverableAuto-filled

DeliverableAuto-filled
Business requirements
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Faisal A. Al-Shehri
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦9%⁩
DueAuto-filled
⁦2024-08-24⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-031_2.1_v1.pdfV1Faisal A. Al-Shehri⁦2024-06-27⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Faisal A. Al-Shehri
Accepted byAuto-filled
Eng. Majed S. Al-Rasheed
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Designs approved
ContractAuto-filled
CTR-2024-009
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Faisal A. Al-ShehriDirector General, Digital Platforms & Digital Services Portfolio ManagerSubmitted—⁦2024-06-27⁩ 10:55
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2024-07-01⁩ 10:13
3Inspection & technical acceptance — ownerTechnical acceptanceEng. Majed S. Al-RasheedProject ownerOn behalf of Faisal A. Al-ShehriApprovedInspected and accepted against the approved acceptance criteria.⁦2024-07-04⁩ 11:20
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2024-07-07⁩ 09:42
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2024-07-09⁩ 10:19

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2024-07-01⁩

Inspection & technical acceptance — owner

Eng. Majed S. Al-Rasheed

Approved⁦2024-07-04⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2024-07-07⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2024-07-09⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Faisal A. Al-Shehri on ⁦2024-06-27⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2024-07-01⁩ at ⁦10:13⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Faisal A. Al-Shehri · Project owner

    Approved · ⁦2024-07-04⁩ at ⁦11:20⁩ · On behalf of Faisal A. Al-Shehri (Eng. Majed S. Al-Rasheed)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2024-07-07⁩ at ⁦09:42⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2024-07-09⁩ at ⁦10:19⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2024-06-27⁩

    PRJ-2026-031_2.1_v1.pdf

    Faisal A. Al-Shehri

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close