Initiation
Project charter
Objective, scope, deliverables, roles and budget
- Form no.
- SCA-PMO-F04
- Template edition
- 3.0
- Version
- V2
- Form date
- 2024-04-05
- Hijri
- 26 Ramadan 1445 AH
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-031
- Project
- Electronic Model Contracts
- Portfolio
- Digital Services & Platforms Portfolio
- Sector
- Regulation & Development Sector
- Sponsor
- Eng. Majed S. Al-Rasheed
- Project manager
- Karim Haddad
1Objective
Background
Draft, sign and register model contracting agreements online, with both parties alerted to obligations and dates.
Project objectives
- Simplify regulatory relationships and make doing business easier
2Scope
In scope
- Draft, sign and register model contracting agreements online, with both parties alerted to obligations and dates.
- Single sign-on through Nafath
- Integration with internal systems
Out of scope
- Operation and maintenance after the warranty period
- Work outside the approved site or system boundary
3Deliverables and milestones
| Deliverable | Due |
|---|---|
| Project management plan | 2024-04-25 |
| Main deliverable — stage 1 | 2024-11-22 |
| Main deliverable — final stage | 2025-04-28 |
| Final report | 2025-06-30 |
| Milestone | Date |
|---|---|
| Charter approved | 2024-04-05 |
| Contract signed | 2024-06-18 |
| 50% of works complete | 2024-11-22 |
| Provisional acceptance | 2025-05-25 |
| Closure | 2025-06-30 |
4RolesAuto-filled
- SponsorAuto-filled
- Eng. Majed S. Al-Rasheed
- Project ownerAuto-filled
- Faisal A. Al-Shehri
- Project managerAuto-filled
- Karim Haddad
| Stakeholder | Role |
|---|---|
| Project sponsor | Decisions and funding |
| Project owner | Accepts deliverables, owns benefits |
| Project Management Office (PMO) | Governance and compliance |
| Governance body | Role | Cadence |
|---|---|---|
| Change Control Board | Approves scope, cost and schedule changes | Weekly |
| PMO Committee | Methodology compliance, data quality, stage gates | Fortnightly |
| Project management team | Day-to-day control, risks, impediments, the periodic update card | Weekly |
5BudgetAuto-filled
| Line | Amount |
|---|---|
| Main contract | SAR 5.9M |
| Supervision & consulting | SAR 1.2M |
| Internal team | SAR 700K |
| Contingency reserve (5%) | SAR 400K |
| Approved budget | SAR 8.2M |
Funding
The owning sector’s approved budget
6Success criteria and constraints
Success criteria
- Delivered within the approved budget
- On the approved date ±5%
- Target benefits within 12 months
Constraints
- Stay within the approved budget
- Comply with the Government Tenders & Procurement Law
Assumptions
- Named internal staff available throughout
- Approvals land within the workflow’s action time limits
Approval logChain: Project charter approval · version 1
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Karim HaddadSenior Digital Delivery Consultant — PMO | Submitted | — | 2024-03-27 10:00 |
| 2 | PMO compliance | Methodology review | Dr. Noura M. Al-OtaibiPMO — director | Approved | — | 2024-03-30 12:30 |
| 3 | Project owner | Technical acceptance | Faisal A. Al-ShehriProject owner | Approved | — | 2024-04-02 09:45 |
| 4 | Budget funding confirmed | Financial approval | Munirah A. Al-KhalidiFinance | Approved | — | 2024-04-03 11:10 |
| 5 | Sponsor approval | Technical acceptance | Eng. Majed S. Al-RasheedProject sponsor | Approved | — | 2024-04-05 11:00 |
Signatures
PMO compliance
Dr. Noura M. Al-Otaibi
Approved2024-03-30
Project owner
Faisal A. Al-Shehri
Approved2024-04-02
Budget funding confirmed
Munirah A. Al-Khalidi
Approved2024-04-03
Sponsor approval
Eng. Majed S. Al-Rasheed
Approved2024-04-05