PRJ-2026-031On track5ClosureScrum

Electronic Model Contracts

Add to watchlist

Draft, sign and register model contracting agreements online, with both parties alerted to obligations and dates.

Budget (BAC)

SAR 8.2M

Actual cost

SAR 8M

⁦97%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 8M

SPI · CPI

1.00Schedule performance index · 1.001.03Cost performance index · 1.03

Forecast finish

⁦2025-07-20⁩

20 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 February 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 April 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate18 June 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate25 May 2025Closure · Current stageClosure · Current stage

Project closure & handover

Performance, handover, open commitments and lessons learned

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Closure

Project closure & handover

Performance, handover, open commitments and lessons learned

Form no.
SCA-PMO-F12
Template edition
2.0
Version
V2
Form date
⁦2025-09-28⁩
Hijri
6 Rabiʻ II 1447 AH
ApprovedPRJ-2026-031Electronic Model Contracts

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-031
Project
Electronic Model Contracts
Portfolio
Digital Services & Platforms Portfolio
Sector
Regulation & Development Sector
Sponsor
Eng. Majed S. Al-Rasheed
Project manager
Karim Haddad

1PerformanceAuto-filled

Approved budget

SAR 8.2M

Actual cost

SAR 8M

Cost variance

SAR +239K

Schedule variance

+20 days

Post-implementation questionVerdictAnswer
Did the project meet its goal?YesYes. Electronic model contracts went live with nine models; over 41K contracting agreements registered on them in year one.
Was it delivered within budget?YesDelivered for SAR 7.96M against 8.2M, 20 days after baseline.
Are the benefits showing?Partly82% realised: satisfaction 82% vs 85% target, 18 minutes to sign a contract vs 15.
Were the lessons captured?YesThree lessons: Nafath environments, payments tied to acceptance, the vendor team.
What to improve next time?PartlyAn SMS alert before contractual due dates, and linking each contract to the company file in Muqawil.

2HandoverAuto-filled

ItemStateOwnerEvidence
Final acceptance of deliverablesDoneFaisal A. Al-ShehriFinal acceptance of 9 deliverables, no open findings
Financial settlementDoneKhalid N. Al-MutairiActual SAR 7.96M of 8.2M — SAR 240K returned to budget
Contracts closedDoneKhalid N. Al-MutairiContract SCA/2024/009 closed, retention released
Documents archivedDoneKarim Haddad64 documents archived with their classification
Lessons learnedDoneKarim Haddad3 lessons published, cited 13 times since
Benefits handed to their ownerDoneEng. Reem K. Al-DosariEng. Reem Al-Dosari owns two benefits with a 24-month plan
Final reportDoneKarim HaddadFinal report approved by the sponsor and the PMO
BenefitNew ownerHandover
Shorter time to sign and register a contractEng. Reem K. Al-DosariAccepted
Higher contractor satisfaction with signing and registering contractsEng. Reem K. Al-DosariAccepted

3Open commitments

CommitmentOwnerDue
No open commitments — the file is complete

4Lessons learnedAuto-filled

  1. Book Nafath test environments three months before build
  2. Tie payments to accepted deliverables, not elapsed time

Approval logChain: Project closure & handover approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Karim HaddadSenior Digital Delivery Consultant — PMOSubmitted—⁦2025-09-16⁩ 12:03
2Closure file completenessMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-09-21⁩ 14:53
3Handover accepted — project ownerTechnical acceptanceFaisal A. Al-ShehriProject ownerApproved—⁦2025-09-22⁩ 09:00
4Final financial settlementFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-09-23⁩ 09:06
5Contracts closed, guarantees releasedFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2025-09-25⁩ 10:43
6Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2025-10-01⁩ 12:21

Signatures

Closure file completeness

Ghada A. Al-Shahrani

Approved⁦2025-09-21⁩

Handover accepted — project owner

Faisal A. Al-Shehri

Approved⁦2025-09-22⁩

Final financial settlement

Munirah A. Al-Khalidi

Approved⁦2025-09-23⁩

Contracts closed, guarantees released

Mazen A. Al-Hazmi

Approved⁦2025-09-25⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2025-10-01⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F12 · version V2

Project closure & handover

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project closure & handover approval · version ⁦1⁩

Submitted by Karim Haddad on ⁦2025-09-16⁩

  1. Methodology review

    Closure file completeness

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-09-21⁩ at ⁦14:53⁩

  2. Technical acceptance

    Handover accepted — project owner

    Faisal A. Al-Shehri · Project owner

    Approved · ⁦2025-09-22⁩ at ⁦09:00⁩

  3. Financial approval

    Final financial settlement

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-09-23⁩ at ⁦09:06⁩

  4. Financial approval

    Contracts closed, guarantees released

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-09-25⁩ at ⁦10:43⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2025-10-01⁩ at ⁦12:21⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-09-28⁩

    The approved closure file