Saudi Contractors AuthorityMunjaz11My actionsNotifications

Lessons learned

Lessons by category, surfaced when a similar project is created.

Published lessons
19

From ⁦17⁩ projects

Times cited
83

In later requests and projects

High impact
10

Cost days or millions

In review
2

Waiting for PMO validation

Where lessons recur

Lessons per category · times cited

Press a category to filter the register.

Suggested for a similar project

Pick a project; lessons rank by type, phase, portfolio and proven reuse.

A Infrastructure project in Planning

  1. 99Same project typeFits its phaseSame portfolioProven
  2. 70Same project typeFits its phase
  3. 70Same project typeFits its phase
  4. 70Same project typeFits its phase
  5. 70Same project typeFits its phase

The register

Each lesson: context, what happened, impact, recommendation.

⁦21⁩ of ⁦21⁩

Tie payments to accepted deliverables, not elapsed time

LL-021 · Finance & funding · Medium impact · Published

  1. 1ContextThe electronic model contracts build contract.
  2. 2What happenedA ⁦20%⁩ payment was released before the stage passed acceptance.
  3. 3ImpactHard to hold the vendor to ⁦37⁩ open defects.

Recommendation

A payment schedule tied to deliverable acceptance in every digital contract.

Captured by
Khalid N. Al-Mutairi
Date
2025-08-307 Rabiʻ I 1447 AH
Applies to
Digital · IT · Service

Where it was used (⁦3⁩)

    Esc

    Quick actions

    Go to

    Projects

    ↑↓to move↵to openEscto close