PRJ-2026-009At risk4ExecutionHybrid
SCA Systems Migration to the Cloud
Add to watchlistMove 46 systems and applications to a licensed in-Kingdom cloud under the data classification framework and cloud controls.
Project managerEng. Omar H. BawazirProject sponsorEng. Majed S. Al-RasheedProgrammeDigital Infrastructure & Security Programme
Budget (BAC)
SAR 52M
Actual cost
SAR 25.2M
48% of budget
Progress
47%Awaiting acceptance 12%
Estimate at completion
SAR 53.6M
SAR +1.6M
SPI · CPI
0.89Schedule performance index · 0.890.97Cost performance index · 0.97
Forecast finish
2027-03-21
21 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure8 January 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate2 April 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate1 June 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate11 September 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate8 January 2027Closure · Not startedClosure · Not started
Periodic update cards
Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.
Periodic update cards
| Period | Status | Progress | Current step | Date |
|---|---|---|---|---|
| October 2026UPD-009-2026-10 | Draft | 47% | — | 2026-10-26 |
| September 2026UPD-009-2026-09 | Approved | 44% | — | 2026-10-02 |
| August 2026UPD-009-2026-08 | Approved | 42% | — | 2026-09-02 |