Portfolio · PF-TECH

Technology & Enterprise Systems Portfolio

At risk

Technology infrastructure, cloud, cybersecurity, enterprise systems, Mimar and the links with government systems.

What-if scenarios
Approved budget
SAR 365M

incl. SAR 12.3M unallocated reserve

Actual spend
SAR 245.7M

⁦67%⁩ of budget

EAC
SAR 376M+3.0%

Estimate at completion

Expected value
SAR 520M

⁦17%⁩ realised

Health score
71−3

was ⁦74⁩ in May

Manager

Eng. Nayef H. Al-Buqami

Director General, Information Technology

Owner

Eng. Majed S. Al-Rasheed

Head, Digital Transformation Sector

AI insight

⁦4⁩ projects in this portfolio are pulling its health down

Most of it comes from “SCA ERP System” (SPI ⁦0.82⁩) and “SCA Systems Migration to the Cloud” (SPI ⁦0.89⁩). Fixing those two lifts the portfolio towards ⁦80⁩ within two quarters.

Confidence⁦81%⁩

Weighted portfolio progress

Σ each project’s relative weight × its actual progress, under the approved project weight model

What each project adds to portfolio progress

The project’s weight from the model, its relative weight among the portfolio’s counted projects, and what it adds

ProjectProject weightRelative weightActual progressWeight × progress
SCA ERP System71.0⁦16.4%⁩⁦61%⁩⁦10.0%⁩
SCA Backup Data Centre71.0⁦16.4%⁩⁦72%⁩⁦11.8%⁩
SCA Systems Migration to the Cloud69.0⁦15.9%⁩⁦47%⁩⁦7.5%⁩
SCA Cybersecurity Programme66.0⁦15.2%⁩⁦88%⁩⁦13.4%⁩
Mimar — Unified Building Journey & Government Integration59.0⁦13.6%⁩⁦6%⁩⁦0.8%⁩
Correspondence & Document Management System (DMS)50.0⁦11.5%⁩⁦95%⁩⁦10.9%⁩
HR Self-Service48.0⁦11.1%⁩⁦100%⁩⁦11.1%⁩
Portfolio progress⁦65.4%⁩

How it is computed

⁦65.4%⁩

Portfolio progress = Σ (project relative weight × actual progress). Relative weight = the project’s weight ÷ the weights of the counted projects, so they add up to 100%.

  • · Proposed and cancelled projects never count.
  • · Left out of this portfolio now: ⁦0⁩
  • · For comparison: weighting by budget alone gives ⁦65.4%⁩

Suspended projects

Open the project weight model

Portfolio health & performance

The health score from eight weighted dimensions, and the schedule and cost indices over six months.

Health-score breakdown

Score × weight = points

71At risk
DimensionScoreWeightPoints
Schedule66⁦20%⁩13.2
Cost74⁦20%⁩14.8
Risk58⁦15%⁩8.7
Scope78⁦10%⁩7.8
Quality80⁦10%⁩8.0
Resources67⁦10%⁩6.7
Stakeholders76⁦5%⁩3.8
Benefits80⁦10%⁩8.0
Total71

Health-score trend

May – October 2026

7471

Financial & schedule performance

May – October 2026

Both indices over time

  • Schedule performance index
  • Cost performance index

Portfolio project map

risk across, strategic value up, bubble size by budget. Click a bubble for a quick look at the project.

Portfolio project map

  • On track
  • At risk
  • Off track
Approved budget · SAR 148M

Funding priority order

Rank the projects for funding; your order is kept and goes to the 2027 planning cycle.

  1. 1SCA Cybersecurity ProgrammePRJ-2026-005·Priority score 85On track
  2. 2SCA Backup Data CentrePRJ-2026-003·Priority score 82At risk
  3. 3SCA Systems Migration to the CloudPRJ-2026-009·Priority score 77At risk
  4. 4SCA ERP SystemPRJ-2026-001·Priority score 74Off track
  5. 5Mimar — Unified Building Journey & Government IntegrationPRJ-2026-011·Priority score 66On track
  6. 6Correspondence & Document Management System (DMS)PRJ-2026-017·Priority score 62At risk

Portfolio priorities 2026–2027

  • Recover the SCA ERPOff track at SPI 0.82 and blocking the case and judgment archive.
  • Host 50% of SCA systems on a licensed in-Kingdom cloudConditional on the SCA backup data centre being ready.
  • Full compliance with the NCA Essential Cybersecurity Controls91% today against a 95% target.

Objectives & KPIs

Why the portfolio exists: the strategic objectives it serves and the KPIs its projects move.

Budget & value

Where the budget goes, why the forecast differs from it, and the value it returns.

From approved budget to estimate at completion

Each programme’s gap between its projects’ budget and their forecast

From approved budget to estimate at completion
  • Total
  • Increase
  • Decrease
From approved budget to estimate at completion
CategoryChangeRunning total
Approved budgetSAR 365MSAR 365M
Unallocated reserve−SAR 12.3MSAR 352.7M
Digital Infrastructure & Security Programme+SAR 15.1MSAR 367.8M
Enterprise Systems & Government Integration Programme+SAR 8.2MSAR 376M
Estimate at completionSAR 376MSAR 376M

Budget use

245.7M/ 365M11Mprojected overrun(⁦3.0%⁩)
Actual spend
245.7M
Committed
294.8M
Approved budget
365M
Estimate at completion
376M

Expected-value mix

Expected-value mix

SAR 520M

Expected value

  • Cost savingSAR 208M⁦40%⁩
  • ProductivitySAR 187.2M⁦36%⁩
  • Time savedSAR 72.8M⁦14%⁩
  • Beneficiary satisfactionSAR 52M⁦10%⁩
Expected-value mix
CategoryValueShare
Cost savingSAR 208M⁦40%⁩
ProductivitySAR 187.2M⁦36%⁩
Time savedSAR 72.8M⁦14%⁩
Beneficiary satisfactionSAR 52M⁦10%⁩
TotalSAR 520M⁦100%⁩

SAR 88.7M

Expected value SAR 520M

⁦92%⁩ of what was planned by today

Programmes & projects

A programme’s performance is computed from its projects. Click a project for a quick look.

⁦7⁩ results
Export CSV
SCA Backup Data CentrePRJ-2026-003PG-034ExecutionAt risk⁦72%⁩⁦16.4%⁩P1P1 · Top priority — score ⁦82⁩ of 100148M162.6M⁦+9.9%⁩0.90Schedule performance index · 0.900.91Cost performance index · 0.91Risk score · Weak
SCA ERP SystemPRJ-2026-001PG-044ExecutionOff track⁦61%⁩⁦16.4%⁩P2P2 · High priority — score ⁦74⁩ of 10064.5M73.3M⁦+13.6%⁩0.82Schedule performance index · 0.820.88Cost performance index · 0.88Risk score · Weak
SCA Systems Migration to the CloudPRJ-2026-009PG-034ExecutionAt risk⁦47%⁩⁦15.9%⁩P1P1 · Top priority — score ⁦77⁩ of 10052M53.6M⁦+3.1%⁩0.89Schedule performance index · 0.890.97Cost performance index · 0.97Risk score · Fair
SCA Cybersecurity ProgrammePRJ-2026-005PG-034ExecutionOn track⁦88%⁩⁦15.2%⁩P1P1 · Top priority — score ⁦85⁩ of 10038.6M37.5M⁦−2.9%⁩1.02Schedule performance index · 1.021.03Cost performance index · 1.03Risk score · Good
Mimar — Unified Building Journey & Government IntegrationPRJ-2026-011PG-043PlanningOn track⁦6%⁩⁦13.6%⁩P2P2 · High priority — score ⁦66⁩ of 10024M24M⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00Risk score · Good
Correspondence & Document Management System (DMS)PRJ-2026-017PG-045ClosureAt risk⁦95%⁩⁦11.5%⁩P2P2 · High priority — score ⁦62⁩ of 10014.2M14.2M⁦0.0%⁩0.95Schedule performance index · 0.951.00Cost performance index · 1.00Risk score · Good
HR Self-ServicePRJ-2026-032PG-045ClosureOn track⁦100%⁩⁦11.1%⁩P2P2 · High priority — score ⁦64⁩ of 10011.4M10.8M⁦−5.7%⁩1.00Schedule performance index · 1.001.06Cost performance index · 1.06Risk score · Excellent
Total · 7352.7M376M
⁦1⁩–⁦7⁩ of ⁦7⁩

Portfolio risks

Open threats across the portfolio’s projects. Click a cell on the map to filter the list.

Latest on this portfolio

14 October 2026

  1. Approval: Project Approval Committee Rework DEC-2026-038SCA ERP project plan sent back for rework