AI insight
4 projects in this portfolio are pulling its health down
Most of it comes from “SCA ERP System” (SPI 0.82) and “SCA Systems Migration to the Cloud” (SPI 0.89). Fixing those two lifts the portfolio towards 80 within two quarters.
Portfolio · PF-TECH
Technology infrastructure, cloud, cybersecurity, enterprise systems, Mimar and the links with government systems.
incl. SAR 12.3M unallocated reserve
67% of budget
Estimate at completion
17% realised
was 74 in May
Manager
Eng. Nayef H. Al-Buqami
Director General, Information Technology
Owner
Eng. Majed S. Al-Rasheed
Head, Digital Transformation Sector
Programmes7 projects
Digital Infrastructure & Security Programme69%Enterprise Systems & Government Integration Programme62%AI insight
Most of it comes from “SCA ERP System” (SPI 0.82) and “SCA Systems Migration to the Cloud” (SPI 0.89). Fixing those two lifts the portfolio towards 80 within two quarters.
Σ each project’s relative weight × its actual progress, under the approved project weight model
The project’s weight from the model, its relative weight among the portfolio’s counted projects, and what it adds
| Project | Project weight | Relative weight | Actual progress | Weight × progress |
|---|---|---|---|---|
| SCA ERP System | 71.0 | 16.4% | 61% | 10.0% |
| SCA Backup Data Centre | 71.0 | 16.4% | 72% | 11.8% |
| SCA Systems Migration to the Cloud | 69.0 | 15.9% | 47% | 7.5% |
| SCA Cybersecurity Programme | 66.0 | 15.2% | 88% | 13.4% |
| Mimar — Unified Building Journey & Government Integration | 59.0 | 13.6% | 6% | 0.8% |
| Correspondence & Document Management System (DMS) | 50.0 | 11.5% | 95% | 10.9% |
| HR Self-Service | 48.0 | 11.1% | 100% | 11.1% |
| Portfolio progress | 65.4% | |||
65.4%
Portfolio progress = Σ (project relative weight × actual progress). Relative weight = the project’s weight ÷ the weights of the counted projects, so they add up to 100%.
The health score from eight weighted dimensions, and the schedule and cost indices over six months.
Score × weight = points
| Dimension | Score | Weight | Points |
|---|---|---|---|
| Schedule | 66 | 20% | 13.2 |
| Cost | 74 | 20% | 14.8 |
| Risk | 58 | 15% | 8.7 |
| Scope | 78 | 10% | 7.8 |
| Quality | 80 | 10% | 8.0 |
| Resources | 67 | 10% | 6.7 |
| Stakeholders | 76 | 5% | 3.8 |
| Benefits | 80 | 10% | 8.0 |
| Total | 71 | ||
Health-score trend
May – October 2026
May – October 2026
0.91
Watch
Schedule performance index
Progress 65% / Planned 70%
0.94
Watch
Cost performance index
Actual spend SAR 245.7M
Both indices over time
risk across, strategic value up, bubble size by budget. Click a bubble for a quick look at the project.
Portfolio project map
Rank the projects for funding; your order is kept and goes to the 2027 planning cycle.
Portfolio priorities 2026–2027
Why the portfolio exists: the strategic objectives it serves and the KPIs its projects move.
88% achieved of a 90% target3 projects contribute
85% achieved of a 90% target2 projects contribute
83% achieved of a 90% target4 projects contribute
Where the budget goes, why the forecast differs from it, and the value it returns.
Each programme’s gap between its projects’ budget and their forecast
| Category | Change | Running total |
|---|---|---|
| Approved budget | SAR 365M | SAR 365M |
| Unallocated reserve | −SAR 12.3M | SAR 352.7M |
| Digital Infrastructure & Security Programme | +SAR 15.1M | SAR 367.8M |
| Enterprise Systems & Government Integration Programme | +SAR 8.2M | SAR 376M |
| Estimate at completion | SAR 376M | SAR 376M |
Budget use
SAR 520M
Expected value
| Category | Value | Share |
|---|---|---|
| Cost saving | SAR 208M | 40% |
| Productivity | SAR 187.2M | 36% |
| Time saved | SAR 72.8M | 14% |
| Beneficiary satisfaction | SAR 52M | 10% |
| Total | SAR 520M | 100% |
Value realised
SAR 88.7M
Expected value SAR 520M
92% of what was planned by today
A programme’s performance is computed from its projects. Click a project for a quick look.
PG-03 · 3 projects
Digital Infrastructure & Security Programme
Planned to date 73%
PG-04 · 4 projects
Enterprise Systems & Government Integration Programme
Planned to date 68%
Display options
| SCA Backup Data CentrePRJ-2026-003 | PG-03 | 4Execution | At risk | 72% | 16.4% | P1P1 · Top priority — score 82 of 100 | 148M | 162.6M+9.9% | 0.90Schedule performance index · 0.90 | 0.91Cost performance index · 0.91 | Risk score · Weak |
| SCA ERP SystemPRJ-2026-001 | PG-04 | 4Execution | Off track | 61% | 16.4% | P2P2 · High priority — score 74 of 100 | 64.5M | 73.3M+13.6% | 0.82Schedule performance index · 0.82 | 0.88Cost performance index · 0.88 | Risk score · Weak |
| SCA Systems Migration to the CloudPRJ-2026-009 | PG-03 | 4Execution | At risk | 47% | 15.9% | P1P1 · Top priority — score 77 of 100 | 52M | 53.6M+3.1% | 0.89Schedule performance index · 0.89 | 0.97Cost performance index · 0.97 | Risk score · Fair |
| SCA Cybersecurity ProgrammePRJ-2026-005 | PG-03 | 4Execution | On track | 88% | 15.2% | P1P1 · Top priority — score 85 of 100 | 38.6M | 37.5M−2.9% | 1.02Schedule performance index · 1.02 | 1.03Cost performance index · 1.03 | Risk score · Good |
| Mimar — Unified Building Journey & Government IntegrationPRJ-2026-011 | PG-04 | 3Planning | On track | 6% | 13.6% | P2P2 · High priority — score 66 of 100 | 24M | 24M0.0% | 1.00Schedule performance index · 1.00 | 1.00Cost performance index · 1.00 | Risk score · Good |
| Correspondence & Document Management System (DMS)PRJ-2026-017 | PG-04 | 5Closure | At risk | 95% | 11.5% | P2P2 · High priority — score 62 of 100 | 14.2M | 14.2M0.0% | 0.95Schedule performance index · 0.95 | 1.00Cost performance index · 1.00 | Risk score · Good |
| HR Self-ServicePRJ-2026-032 | PG-04 | 5Closure | On track | 100% | 11.1% | P2P2 · High priority — score 64 of 100 | 11.4M | 10.8M−5.7% | 1.00Schedule performance index · 1.00 | 1.06Cost performance index · 1.06 | Risk score · Excellent |
| Total · 7 | 352.7M | 376M |
Open threats across the portfolio’s projects. Click a cell on the map to filter the list.
8 risks
Impact
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 0 · Low | 0 · Medium | 0 · High | 0 · Critical | 0 · Critical |
| 4 | 0 · Low | 0 · Medium | 2 · Medium | 2 · High | 0 · Critical |
| 3 | 0 · Low | 0 · Low | 3 · Medium | 0 · Medium | 0 · High |
| 2 | 0 · Low | 0 · Low | 0 · Low | 0 · Medium | 1 · Medium |
| 1 | 0 · Low | 0 · Low | 0 · Low | 0 · Low | 0 · Low |
Top risks
Approval: Project Approval Committee Rework DEC-2026-038SCA ERP project plan sent back for rework
2026-10-14 10:00