Late historic-data migration delays the financial close and the archive link-up
PRK-04-1·Mitigate·Dana S. Al-Saleh
Programme · PG-04 · Technology & Enterprise Systems Portfolio
ERP, Mimar and government integration, document management and employee self-service.
incl. SAR 4M programme reserve
60% of budget
Estimate at completion
Planned 68%
Cost performance index 0.94
Manager
Dana S. Al-Saleh
Director, Enterprise Systems & Integration
Sponsor
Sarah A. Al-Qarni
Head, Corporate Support Sector
Projects
4 projects
2024-05-05 — 2027-12-30
On track 2At risk 1Off track 1
What the programme must achieve, and the strategic objectives it serves.
One SCA ERP for finance, procurement, HR and assets
One electronic archive for cases, judgments and administrative correspondence
Self-service for 90% of staff transactions
Serves strategic objectives
From baseline to target
Spend-rationalisation savings
by 2027Staff hours saved by automation
by 2027One lane per project: start to forecast finish, with the progress earned and the baseline finish.
What waits on what. Red links are on the programme’s critical path.
Critical path
Critical
Archive access rights are built on the org structure and staff register in the ERP
Self-service processes fold into the HR module
Payment documents are archived from the correspondence system
Risks that hit more than one project, managed at programme level.
Late historic-data migration delays the financial close and the archive link-up
PRK-04-1·Mitigate·Dana S. Al-Saleh
Resistance from users of paper processes
PRK-04-2·Mitigate·Nouf M. Al-Balawi
4 risks
Impact
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 0 · Low | 0 · Medium | 0 · High | 0 · Critical | 0 · Critical |
| 4 | 0 · Low | 0 · Medium | 1 · Medium | 1 · High | 0 · Critical |
| 3 | 0 · Low | 0 · Low | 2 · Medium | 0 · Medium | 0 · High |
| 2 | 0 · Low | 0 · Low | 0 · Low | 0 · Medium | 0 · Medium |
| 1 | 0 · Low | 0 · Low | 0 · Low | 0 · Low | 0 · Low |
Savings from spend rationalisation
61SAR M
+6
Target 8572%
Projects compliant with the delivery methodology
84%
+2
Target 90%93%
Approved budget executed
77%
+7
Target 95%81%
Employee engagement index
71%
+1
Target 75%95%
Power against interest; click a person to see their role.
Keep satisfied0
Manage closely3
Monitor0
Keep informed1
Interest
What the committees decided on the programme’s projects, and what the programme raised to them.
Committees
Monthly · Quorum 5
Members
6 members
Fortnightly · Quorum 4
Members
7 members
Weekly · Quorum 4
Members
5 members
The programme’s performance is computed from these projects.
Display options
| Manager | ||||||||
|---|---|---|---|---|---|---|---|---|
| SCA ERP SystemPRJ-2026-001 | Dana S. Al-Saleh | 4Execution | Off track | 61% | 64.5M | 73.3M+13.6% | 0.82Schedule performance index · 0.82 | 0.88Cost performance index · 0.88 |
| Mimar — Unified Building Journey & Government IntegrationPRJ-2026-011 | Dana S. Al-Saleh | 3Planning | On track | 6% | 24M | 24M0.0% | 1.00Schedule performance index · 1.00 | 1.00Cost performance index · 1.00 |
| Correspondence & Document Management System (DMS)PRJ-2026-017 | Dana S. Al-Saleh | 5Closure | At risk | 95% | 14.2M | 14.2M0.0% | 0.95Schedule performance index · 0.95 | 1.00Cost performance index · 1.00 |
| HR Self-ServicePRJ-2026-032 | Dana S. Al-Saleh | 5Closure | On track | 100% | 11.4M | 10.8M−5.7% | 1.00Schedule performance index · 1.00 | 1.06Cost performance index · 1.06 |
| Total · 4 | 114.1M | 122.3M |
SAR 114.1M
Budget
| Category | Value | Share |
|---|---|---|
| SCA ERP System | SAR 64.5M | 57% |
| Mimar — Unified Building Journey & Government Integration | SAR 24M | 21% |
| Correspondence & Document Management System (DMS) | SAR 14.2M | 12% |
| HR Self-Service | SAR 11.4M | 10% |
| Total | SAR 114.1M | 100% |