Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-011On track3PlanningWaterfall

Mimar — Unified Building Journey & Government Integration

Add to watchlist

One journey for contractors and owners from permit to handover, linked with Balady, Etimad, Qiwa and the commercial register.

Budget (BAC)

SAR 24M

Actual cost

SAR 1.4M

⁦6%⁩ of budget

Progress

⁦6%⁩Awaiting acceptance ⁦4%⁩

Estimate at completion

SAR 24M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-30⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution30 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 May 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 July 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate30 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

+7

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦6%⁩ done against ⁦6%⁩ planned.

SPI ⁦1.00⁩, CPI ⁦1.00⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: A Leading, Sustainable OrganisationSO-4.3A sustainable financial base

Main initiative

Under no initiative — listed under «projects with no strategic link»

Secondary links

No secondary links

Annual work-plan line
WP-2026-011
Classification
External

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦6%⁩

Awaiting acceptance ⁦4%⁩

Not handed in ⁦90%⁩

1 deliverable accepted

  • Project plan & baseline⁦6%⁩

1 deliverable under inspection or acceptance

  • Monitoring & reporting⁦4%⁩

Progress & earned value

⁦2⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦8%⁩ of budget

1.4M/ 24M
Actual spend
1.4M
Committed
1.9M
Approved budget
24M
Estimate at completion
24M

Next milestones

  • 50% of works complete⁦2027-04-08⁩On track
  • Provisional acceptance⁦2027-11-17⁩On track
  • Closure⁦2027-12-30⁩On track

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Change requests

Cost and schedule impact

  • No change requests

Risks & impediments

0 open risks, exposure SAR 0

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium0
  • Low0

Top risks

  • No open risks

Open impediments

⁦0⁩ escalated

  • No open impediments

Deliverables

⁦1⁩ of ⁦11⁩ approved

  • Project plan & baseline011-D1 · V1 · CRT-011-01⁦6%⁩Dana S. Al-Saleh⁦2026-09-18⁩2026-09-187 Rabiʻ II 1448 AHApproved
  • Monitoring & reporting011-D2 · V1⁦4%⁩Munirah A. Al-KhalidiIn 7 days2026-11-0424 Jumada I 1448 AHSubmitted
  • Business requirements011-D3 · V0⁦8%⁩Munirah A. Al-KhalidiIn 54 days2026-12-2112 Rajab 1448 AHDraft
  • Solution design011-D4 · V0⁦8%⁩Sarah A. Al-QarniIn 100 days2027-02-0528 Shaʻban 1448 AHDraft
  • Release 1011-D5 · V0⁦13%⁩Sarah A. Al-QarniIn 147 days2027-03-2416 Shawwal 1448 AHDraft
  • Release 2011-D6 · V0⁦13%⁩Dana S. Al-SalehIn 194 days2027-05-104 Dhuʻl-Hijjah 1448 AHDraft
  • Integrations011-D7 · V0⁦13%⁩Munirah A. Al-KhalidiIn 241 days2027-06-2621 Muharram 1449 AHDraft
  • System testing011-D8 · V0⁦10%⁩Dana S. Al-SalehIn 288 days2027-08-1210 Rabiʻ I 1449 AHDraft
  • User acceptance testing011-D9 · V0⁦10%⁩Munirah A. Al-KhalidiIn 334 days2027-09-2726 Rabiʻ II 1449 AHDraft
  • Training & change011-D10 · V0⁦8%⁩Munirah A. Al-KhalidiIn 381 days2027-11-1314 Jumada II 1449 AHDraft
  • Go-live & handover011-D11 · V0⁦7%⁩Sarah A. Al-QarniIn 428 days2027-12-302 Shaʻban 1449 AHDraft

Team, contracts & documents

Team

3 members

Dana S. Al-Saleh · Director, Enterprise Systems & IntegrationEng. Laila Mansour · Enterprise Architecture & Integration ConsultantEng. Asma S. Al-Hamdan · Enterprise Architect
  • Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationProject managerP-025d.alsaleh@sca.sa⁦20%⁩
  • Eng. Laila MansourEng. Laila MansourEnterprise Architecture & Integration ConsultantIntegration adviser, Mimar to agency systemsP-042l.mansour@sca.sa⁦35%⁩
  • Eng. Asma S. Al-HamdanEng. Asma S. Al-HamdanEnterprise ArchitectUnified-journey architecture & Balady/Etimad linksP-031a.alhamdan@sca.sa⁦30%⁩

Contracts

0 contracts

  • No external contracts — delivered in-house

Documents

  • No documents yet

Meetings

  • No meetings scheduled
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close