Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-011On track3PlanningWaterfall

Mimar — Unified Building Journey & Government Integration

Add to watchlist

One journey for contractors and owners from permit to handover, linked with Balady, Etimad, Qiwa and the commercial register.

Budget (BAC)

SAR 24M

Actual cost

SAR 1.4M

⁦6%⁩ of budget

Progress

⁦6%⁩Awaiting acceptance ⁦4%⁩

Estimate at completion

SAR 24M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-30⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution30 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 May 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 July 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate30 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 24M split into spent, committed and left, with the estimate at completion

EAC SAR 24M
Revised request SAR 24M
  • Actual spendSAR 1.4M
  • Committed, not spentSAR 460K
  • Allotted, uncommittedSAR 21.4M
  • Contingency availableSAR 720K

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 24.5M
Original budgetwhen the first baseline was approved
SAR 24M
Approved budgetafter approved change requests
SAR 24M
Current budgetavailable to spend now
SAR 24M
Revised budgetif the pending changes are approved
SAR 24M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 1.9M
Contracts0 active contracts
SAR 0
Purchase orders⁦2⁩ orders
SAR 1.9M
Remaining budgetapproved less actual
SAR 22.6M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 1.4M
Accrualswork done, not yet invoiced
SAR 58K
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 24M
ContingencySAR 480K drawn of SAR 1.2M
SAR 720K

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 24.5M
ApprovedSAR 24M
Estimate at completionSAR 24M
Approved is SAR 500K (⁦2.0%⁩) below the estimate
The estimate at completion is SAR 500K (⁦2.0%⁩) below the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2026-04-21⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-61011
  • WBS elements⁦5⁩ elements · P-2026-011.01 …
  • Purchase orders⁦2⁩ synced · ⁦0⁩ manual
  • Invoices & certificatesNo certificates
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 480K drawn of SAR 1.2M

  • Covering realised delivery risks⁦2026-08-29⁩SAR 480K

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance1.861.451.441.87⁦−0.01⁩
2Analysis & design3.960.080.004.02⁦−0.07⁩
3Build9.310.200.009.47⁦−0.15⁩
4Testing & acceptance4.660.100.004.73⁦−0.08⁩
5Launch & handover3.490.070.003.55⁦−0.06⁩
Unallocated contingency0.720.000.000.36⁦+0.36⁩
Total24.001.901.4424.00⁦+0.00⁩

Budget split

WBS

SAR 24M

Budget

  • Management & governanceSAR 1.9M⁦8%⁩
  • Analysis & designSAR 4M⁦16%⁩
  • BuildSAR 9.3M⁦39%⁩
  • Testing & acceptanceSAR 4.7M⁦19%⁩
  • Launch & handoverSAR 3.5M⁦15%⁩
  • Unallocated contingencySAR 720K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2028-10-03⁩+278

SPI(t) ⁦0.66⁩ against the approved finish ⁦2027-12-30⁩

Planned valuePV
SAR 3M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 1.4M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 1.4M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 24M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.00⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−1.59⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.00
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.48
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 24M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 22.6M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.00⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.00
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 24M
  • If the rest goes to planSAR 24M
  • At cost and schedule performanceSAR 48.9M
  • The PM’s bottom-up estimateSAR 24M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SAR 24M

Variance at completion: ⁦+0.00⁩ SAR M

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close