PRJ-2026-011On track3PlanningWaterfall

Mimar — Unified Building Journey & Government Integration

Add to watchlist

One journey for contractors and owners from permit to handover, linked with Balady, Etimad, Qiwa and the commercial register.

Budget (BAC)

SAR 24M

Actual cost

SAR 1.4M

⁦6%⁩ of budget

Progress

⁦6%⁩Awaiting acceptance ⁦4%⁩

Estimate at completion

SAR 24M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-30⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution30 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 May 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 July 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate30 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work23.3M⁦16⁩ elements
Unallocated contingency720KSAR 1.2M
Budget at completion24MPRJ-2026-011
Weighted progress⁦6%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project548⁦2026-07-05⁩⁦2028-01-04⁩⁦6%⁩23.281.44—
1
Phase152⁦2026-07-05⁩⁦2026-12-04⁩⁦75%⁩1.861.44—
1.1
WBS element113⁦2026-07-05⁩⁦2026-10-26⁩⁦100%⁩0.930.960 / 1
1.2
WBS element105⁦2026-08-21⁩⁦2026-12-04⁩⁦50%⁩0.930.481 / 2
2
Phase114⁦2026-11-08⁩⁦2027-03-02⁩⁦0%⁩3.96——
2.1
WBS element70⁦2026-11-08⁩⁦2027-01-17⁩⁦0%⁩1.98—1 / 1
2.2
WBS element70⁦2026-12-22⁩⁦2027-03-02⁩⁦0%⁩1.98—1 / 2
3
Phase158⁦2027-02-04⁩⁦2027-07-12⁩⁦0%⁩9.31——
3.1
WBS element70⁦2027-02-04⁩⁦2027-04-15⁩⁦0%⁩3.10—1 / 1
3.2
WBS element70⁦2027-03-20⁩⁦2027-05-29⁩⁦0%⁩3.10—1 / 1
3.3
WBS element70⁦2027-05-03⁩⁦2027-07-12⁩⁦0%⁩3.10—1 / 2
4
Phase114⁦2027-06-16⁩⁦2027-10-08⁩⁦0%⁩4.66——
4.1
WBS element70⁦2027-06-16⁩⁦2027-08-25⁩⁦0%⁩2.33—1 / 1
4.2
WBS element70⁦2027-07-30⁩⁦2027-10-08⁩⁦0%⁩2.33—1 / 2
5
Phase114⁦2027-09-12⁩⁦2028-01-04⁩⁦0%⁩3.49——
5.1
WBS element70⁦2027-09-12⁩⁦2027-11-21⁩⁦0%⁩1.75—1 / 1
5.2
WBS element70⁦2027-10-26⁩⁦2028-01-04⁩⁦0%⁩1.75—1 / 1
Total⁦6%⁩23.281.44