PRJ-2026-011On track3PlanningWaterfall

Mimar — Unified Building Journey & Government Integration

Add to watchlist

One journey for contractors and owners from permit to handover, linked with Balady, Etimad, Qiwa and the commercial register.

Budget (BAC)

SAR 24M

Actual cost

SAR 1.4M

⁦6%⁩ of budget

Progress

⁦6%⁩Awaiting acceptance ⁦4%⁩

Estimate at completion

SAR 24M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-30⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution30 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 May 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 July 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate30 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+5⁩ days vs approved

Baseline (original = approved)⁦2027-12-30⁩
Current forecast⁦2028-01-04⁩
By earned schedule⁦2028-10-03⁩
Critical activities
11
of ⁦15⁩ open activities
Late activities
10
past their baseline finish
Schedule performance
0.48
earned ÷ planned value
Next milestone
in 37 days
Project plan approved
Expand allCollapse all
Activity
Mimar — Unified Building Journey & Government IntegrationPlanned: ⁦2026-07-05⁩ → ⁦2027-12-30⁩Forecast: ⁦2026-07-05⁩ → ⁦2028-01-04⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2026-07-05⁩ → ⁦2026-11-04⁩Forecast: ⁦2026-07-05⁩ → ⁦2026-12-04⁩Float: ⁦0⁩d
Project plan & baselinePlanned: ⁦2026-07-05⁩ → ⁦2026-09-18⁩Actual: ⁦2026-07-05⁩ → ⁦2026-10-26⁩
Monitoring & reportingPlanned: ⁦2026-08-21⁩ → ⁦2026-11-04⁩Forecast: ⁦2026-08-21⁩ → ⁦2026-12-04⁩Float: ⁦0⁩dDrag to change its duration+30
Project plan approvedPlanned: ⁦2026-11-04⁩ → ⁦2026-11-04⁩Forecast: ⁦2026-12-04⁩ → ⁦2026-12-04⁩Float: ⁦396⁩dDrag to change its datesProject plan approved
Analysis & designPlanned: ⁦2026-10-07⁩ → ⁦2027-02-05⁩Forecast: ⁦2026-11-08⁩ → ⁦2027-03-02⁩Float: ⁦0⁩d
Business requirementsPlanned: ⁦2026-10-07⁩ → ⁦2026-12-21⁩Forecast: ⁦2026-11-08⁩ → ⁦2027-01-17⁩Float: ⁦0⁩dDrag to change its dates+27
Solution designPlanned: ⁦2026-11-22⁩ → ⁦2027-02-05⁩Forecast: ⁦2026-12-22⁩ → ⁦2027-03-02⁩Float: ⁦0⁩dDrag to change its dates+25
Designs approvedPlanned: ⁦2027-02-05⁩ → ⁦2027-02-05⁩Forecast: ⁦2027-03-02⁩ → ⁦2027-03-02⁩Float: ⁦308⁩dDrag to change its datesDesigns approved
BuildPlanned: ⁦2027-01-08⁩ → ⁦2027-06-26⁩Forecast: ⁦2027-02-04⁩ → ⁦2027-07-12⁩Float: ⁦0⁩d
Release 1Planned: ⁦2027-01-08⁩ → ⁦2027-03-24⁩Forecast: ⁦2027-02-04⁩ → ⁦2027-04-15⁩Float: ⁦0⁩dDrag to change its dates+22
Release 2Planned: ⁦2027-02-24⁩ → ⁦2027-05-10⁩Forecast: ⁦2027-03-20⁩ → ⁦2027-05-29⁩Float: ⁦0⁩dDrag to change its dates+19
IntegrationsPlanned: ⁦2027-04-12⁩ → ⁦2027-06-26⁩Forecast: ⁦2027-05-03⁩ → ⁦2027-07-12⁩Float: ⁦0⁩dDrag to change its dates+16
Build completePlanned: ⁦2027-06-26⁩ → ⁦2027-06-26⁩Forecast: ⁦2027-07-12⁩ → ⁦2027-07-12⁩Float: ⁦176⁩dDrag to change its datesBuild complete
Testing & acceptancePlanned: ⁦2027-05-29⁩ → ⁦2027-09-27⁩Forecast: ⁦2027-06-16⁩ → ⁦2027-10-08⁩Float: ⁦0⁩d
System testingPlanned: ⁦2027-05-29⁩ → ⁦2027-08-12⁩Forecast: ⁦2027-06-16⁩ → ⁦2027-08-25⁩Float: ⁦0⁩dDrag to change its dates+13
User acceptance testingPlanned: ⁦2027-07-14⁩ → ⁦2027-09-27⁩Forecast: ⁦2027-07-30⁩ → ⁦2027-10-08⁩Float: ⁦0⁩dDrag to change its dates+11
Testing & acceptance completePlanned: ⁦2027-09-27⁩ → ⁦2027-09-27⁩Forecast: ⁦2027-10-08⁩ → ⁦2027-10-08⁩Float: ⁦88⁩dDrag to change its datesTesting & acceptance complete
Launch & handoverPlanned: ⁦2027-08-30⁩ → ⁦2027-12-30⁩Forecast: ⁦2027-09-12⁩ → ⁦2028-01-04⁩Float: ⁦0⁩d
Training & changePlanned: ⁦2027-08-30⁩ → ⁦2027-11-13⁩Forecast: ⁦2027-09-12⁩ → ⁦2027-11-21⁩Float: ⁦0⁩dDrag to change its dates+8
Go-live & handoverPlanned: ⁦2027-10-16⁩ → ⁦2027-12-30⁩Forecast: ⁦2027-10-26⁩ → ⁦2028-01-04⁩Float: ⁦0⁩dDrag to change its dates+5
Final handoverPlanned: ⁦2027-12-30⁩ → ⁦2027-12-30⁩Forecast: ⁦2028-01-04⁩ → ⁦2028-01-04⁩Float: ⁦0⁩dDrag to change its datesFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦22⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦15⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦10⁩ activities with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“Monitoring & reporting” needs a pace ⁦1.8⁩× faster than it has kept

It earned ⁦50%⁩ in 68 days; the forecast assumes the rest in 37 days. At the pace so far it finishes on ⁦2027-01-04⁩.

The critical chain

In date order, to final acceptance