PRJ-2026-011On track3PlanningWaterfall

Mimar — Unified Building Journey & Government Integration

Add to watchlist

One journey for contractors and owners from permit to handover, linked with Balady, Etimad, Qiwa and the commercial register.

Budget (BAC)

SAR 24M

Actual cost

SAR 1.4M

⁦6%⁩ of budget

Progress

⁦6%⁩Awaiting acceptance ⁦4%⁩

Estimate at completion

SAR 24M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-30⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution30 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 May 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 July 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate30 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Periodic update cards

Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.

Period

October 2026

Draft
Progress
⁦6%⁩
Planned
⁦6%⁩
SPI
1.00
Open the card

Periodic update cards

PeriodStatusProgressCurrent stepDate
October 2026UPD-011-2026-10Draft⁦6%⁩—⁦2026-10-26⁩
September 2026UPD-011-2026-09Approved⁦4%⁩—⁦2026-10-02⁩
August 2026UPD-011-2026-08Approved⁦2%⁩—⁦2026-09-02⁩