RSK-0012SCA ERP System

Customisation and Etimad integration costs exceeding the approved contingency

16HighEscalatedMaterial

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Customisations missed in the tender book, and an Etimad integration harder than expected

Preventive controls

  • Freeze all non-mandatory customisations
  • Change request to raise the customisation & integration budget
  • Independent review of the vendor’s estimates

1 / 3

Event

Customisation and Etimad integration costs exceeding the approved contingency

16HighTrigger

The budget increase is refused, or spend passes 95% of contingency

Contingency

Move the asset module to a second phase after the financial go-live

Impact

The contingency fully consumed and SAR 6.8M of extra budget requested

SAR 6.8M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
16High

Residual

5
4
3
2
1
1
2
3
4
5
9Medium

Exposure

SAR 6.8M

Residual

⁦44⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 5 days ago

  1. Project manager

    Dana S. Al-Saleh

    Currently followed up here
  2. Programme manager

    Current level

    Dana S. Al-Saleh

    Automatically at 15 days unreviewed · in 10 days
  3. 3

    PMO director

    Dr. Noura M. Al-Otaibi

    Automatically at 20 days unreviewed · in 15 days
  4. 4

    Executive committee

    Dr. Abdullah S. Al-Qahtani

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦2⁩ of ⁦3⁩ done
  • Freeze all non-mandatory customisations

    Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.sa
    Done⁦2026-10-30⁩2026-10-3019 Jumada I 1448 AH
  • Change request to raise the customisation & integration budget

    Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.sa
    Done⁦2026-10-09⁩2026-10-0928 Rabiʻ II 1448 AH
  • Independent review of the vendor’s estimates

    Haifa S. Al-RuwailiHaifa S. Al-RuwailiSenior Financial AnalystP-037h.alruwaili@sca.sa
    In progressIn 11 days2026-11-0828 Jumada I 1448 AH

Trigger

The budget increase is refused, or spend passes 95% of contingency

Contingency

Move the asset module to a second phase after the financial go-live

Esc