RSK-0012SCA ERP System
Customisation and Etimad integration costs exceeding the approved contingency
A risk's detail, response, contingency and residual risk.
Risk statement
From cause to event to impact — with the preventive controls before the event and the contingency after it
Cause
Customisations missed in the tender book, and an Etimad integration harder than expected
Preventive controls
- Freeze all non-mandatory customisations
- Change request to raise the customisation & integration budget
- Independent review of the vendor’s estimates
1 / 3
Event
Customisation and Etimad integration costs exceeding the approved contingency
The budget increase is refused, or spend passes 95% of contingency
Contingency
Move the asset module to a second phase after the financial go-live
Impact
The contingency fully consumed and SAR 6.8M of extra budget requested
Assessment
The level before and after the response
Inherent
Residual
Exposure
SAR 6.8M
Residual
44% off the score
Score trend
Last six months
- Score
- Target residual
Escalation path
Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director
Last reviewed 5 days ago
Project manager
Dana S. Al-Saleh
Currently followed up hereProgramme manager
Current levelDana S. Al-Saleh
Automatically at 15 days unreviewed · in 10 days- 3
PMO director
Dr. Noura M. Al-Otaibi
Automatically at 20 days unreviewed · in 15 days - 4
Executive committee
Dr. Abdullah S. Al-Qahtani
By the PMO director’s decision
Mitigation plan
Each action with its owner and date — tick it off when complete
Freeze all non-mandatory customisations
Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.saDone2026-10-302026-10-3019 Jumada I 1448 AHChange request to raise the customisation & integration budget
Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationP-025d.alsaleh@sca.saDone2026-10-092026-10-0928 Rabiʻ II 1448 AHIndependent review of the vendor’s estimates
Haifa S. Al-RuwailiHaifa S. Al-RuwailiSenior Financial AnalystP-037h.alruwaili@sca.saIn progressIn 11 days2026-11-0828 Jumada I 1448 AH
Trigger
The budget increase is refused, or spend passes 95% of contingency
Contingency
Move the asset module to a second phase after the financial go-live