Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-001Off track4ExecutionHybrid

SCA ERP System

Remove from watchlist

One integrated system for the Authority’s finance, procurement and HR, connected to the Etimad platform.

Early warning: ⁦86%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 64.5M

Actual cost

SAR 44.7M

⁦69%⁩ of budget

Progress

⁦61%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 73.3M

SAR +8.8M

SPI · CPI

0.82Schedule performance index · 0.820.88Cost performance index · 0.88

Forecast finish

⁦2027-02-27⁩

58 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate7 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 November 2026Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−23

May to October 2026

No material change in the health dimensions over the period.

AI insight

⁦86%⁩ chance of a further slip within ⁦30⁩ days

From the SPI trend (⁦0.82⁩), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.

Confidence⁦82%⁩

Copilot summary

Generated from the live project data

The project is behind plan: ⁦61%⁩ done against ⁦74%⁩ planned.

SPI ⁦0.82⁩, CPI ⁦0.88⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: A Leading, Sustainable OrganisationSO-4.3A sustainable financial base

Main initiative

SI-4.2.1Enterprise automation & government integration

Contribution to the initiative⁦72%⁩

The project’s share of the initiative’s project budget (3 projects)

Secondary links

Annual work-plan line
WP-2025-001
Classification
Operational

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦61%⁩

Awaiting acceptance ⁦11%⁩

Not handed in ⁦28%⁩

6 deliverables accepted

  • Release 1⁦16%⁩
  • Release 2⁦16%⁩
  • Business requirements⁦10%⁩
  • Solution design⁦10%⁩
  • Project plan & baseline⁦5%⁩
  • Monitoring & reporting⁦4%⁩

1 deliverable under inspection or acceptance

  • Integrations⁦11%⁩

Corrective planCP-2026-05

Sent back

Customisations and integrations missed in the tender book, the Etimad link failing twice, and late migration of historical financial data

Actions

⁦1⁩ of ⁦4⁩ done

Next: A joint fix session with the Etimad team · Dana S. Al-Saleh · 2026-10-30

Days won back

⁦10⁩ of ⁦32⁩

With the plan: 2027-02-27

Open the plan

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦81%⁩ of budget

44.7M/ 64.5M8.8Mprojected overrun(⁦13.6%⁩)
Actual spend
44.7M
Committed
52.4M
Approved budget
64.5M
Estimate at completion
73.3M

Next milestones

  • Provisional acceptance⁦2026-12-18⁩was ⁦2026-11-04⁩Late
  • Closure⁦2027-02-27⁩was ⁦2026-12-31⁩Late

Waiting on someone

⁦2⁩ approvals and ⁦2⁩ open actions on this project

Approvals & requests

From «My actions» for this project

Actions

⁦2⁩ open

  • Re-baseline the plan per committee commentsDana S. Al-SalehIn 7 days2026-11-0424 Jumada I 1448 AHHigh
  • Joint fix session with the Etimad teamEng. Asma S. Al-HamdanIn 2 days2026-10-3019 Jumada I 1448 AHHigh

Risks & impediments

3 open risks, exposure SAR 9.8M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩1Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩RSK-0013Late migration and reconciliation of historical financial data1Probability: Likely · Impact: MajorHigh · Score ⁦16⁩RSK-0012Customisation and Etimad integration costs exceeding the approved contingencyProbability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩1Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩RSK-0014Implementation consultants’ contracts ending before go-liveProbability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High1
  • Medium2
  • Low0

Deliverables

⁦6⁩ of ⁦11⁩ approved

  • Project plan & baseline001-D1 · V1 · CRT-001-01⁦5%⁩Dana S. Al-Saleh⁦2025-04-21⁩2025-04-2123 Shawwal 1446 AHApproved
  • Monitoring & reporting001-D2 · V1 · CRT-001-02⁦4%⁩Munirah A. Al-Khalidi⁦2025-06-22⁩2025-06-2226 Dhuʻl-Hijjah 1446 AHApproved
  • Business requirements001-D3 · V1 · CRT-001-03⁦10%⁩Munirah A. Al-Khalidi⁦2025-08-23⁩2025-08-2329 Safar 1447 AHApproved
  • Solution design001-D4 · V1 · CRT-001-04⁦10%⁩Sarah A. Al-Qarni⁦2025-10-24⁩2025-10-242 Jumada I 1447 AHApproved
  • Release 1001-D5 · V1 · CRT-001-05⁦16%⁩Sarah A. Al-Qarni⁦2025-12-25⁩2025-12-255 Rajab 1447 AHApproved
  • Release 2001-D6 · V1 · CRT-001-06⁦16%⁩Dana S. Al-Saleh⁦2026-02-25⁩2026-02-258 Ramadan 1447 AHApproved
  • Integrations001-D7 · V1⁦11%⁩Munirah A. Al-Khalidi184 days overdue2026-04-2710 Dhuʻl-Qiʻdah 1447 AHIn review
  • System testing001-D8 · V0⁦8%⁩Dana S. Al-Saleh122 days overdue2026-06-2813 Muharram 1448 AHDraft
  • User acceptance testing001-D9 · V0⁦8%⁩Munirah A. Al-Khalidi60 days overdue2026-08-2916 Rabiʻ I 1448 AHDraft
  • Training & change001-D10 · V0⁦6%⁩Munirah A. Al-KhalidiIn 2 days2026-10-3019 Jumada I 1448 AHDraft
  • Go-live & handover001-D11 · V0⁦6%⁩Sarah A. Al-QarniIn 64 days2026-12-3122 Rajab 1448 AHDraft

Team, contracts & documents

Team

4 members

Dana S. Al-Saleh · Director, Enterprise Systems & IntegrationEng. Asma S. Al-Hamdan · Enterprise ArchitectHaifa S. Al-Ruwaili · Senior Financial Analyst
  • Dana S. Al-SalehDana S. Al-SalehDirector, Enterprise Systems & IntegrationProject managerP-025d.alsaleh@sca.sa⁦60%⁩
  • Eng. Asma S. Al-HamdanEng. Asma S. Al-HamdanEnterprise ArchitectSCA ERP solution architectureP-031a.alhamdan@sca.sa⁦40%⁩
  • Haifa S. Al-RuwailiHaifa S. Al-RuwailiSenior Financial AnalystFinancial analystP-037h.alruwaili@sca.sa⁦10%⁩

Documents

  • No documents yet

Meetings

  • No meetings scheduled
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close