AI insight
86% chance of a further slip within 30 days
From the SPI trend (0.82), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.
One integrated system for the Authority’s finance, procurement and HR, connected to the Etimad platform.
Budget (BAC)
Actual cost
69% of budget
Progress
Estimate at completion
SAR +8.8M
SPI · CPI
Forecast finish
58 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure4 November 2026
A weighted index, not just percent complete; each dimension leads to the tab that explains it.
Health index
70
Needs watching
Index over the last six reports
May to October 2026
No material change in the health dimensions over the period.
AI insight
From the SPI trend (0.82), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.
Generated from the live project data
The project is behind plan: 61% done against 74% planned.
SPI 0.82, CPI 0.88.
How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.
The main objective and initiative, the secondary links, and the project’s contribution to its initiative.
Main initiative
SI-4.2.1Enterprise automation & government integration
The project’s share of the initiative’s project budget (3 projects)
Secondary links
Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.
Counted
61%Awaiting acceptance 11%
Not handed in 28%
6 deliverables accepted
1 deliverable under inspection or acceptance
Corrective planCP-2026-05
Sent back
Customisations and integrations missed in the tender book, the Etimad link failing twice, and late migration of historical financial data
Actions
1 of 4 done
Next: A joint fix session with the Etimad team · Dana S. Al-Saleh · 2026-10-30
Days won back
10 of 32
With the plan: 2027-02-27
3 of 5 milestones complete
Earned-value curve
Planned, earned and actual to the data date, cumulative, with the forecast cost tail
Commitments are 81% of budget
2 approvals and 2 open actions on this project
From «My actions» for this project
2 open
Cost and schedule impact
3 open risks, exposure SAR 9.8M
Impact
6 of 11 approved
4 members