PRJ-2026-001Off track4ExecutionHybrid
SCA ERP System
Remove from watchlistOne integrated system for the Authority’s finance, procurement and HR, connected to the Etimad platform.
Project managerDana S. Al-SalehProject sponsorSarah A. Al-QarniProgrammeEnterprise Systems & Government Integration Programme
Early warning: 86% chance of slipping within 30 days
Budget (BAC)
SAR 64.5M
Actual cost
SAR 44.7M
69% of budget
Progress
61%Awaiting acceptance 11%
Estimate at completion
SAR 73.3M
SAR +8.8M
SPI · CPI
0.82Schedule performance index · 0.820.88Cost performance index · 0.88
Forecast finish
2027-02-27
58 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure4 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate7 May 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate4 November 2026Closure · Not startedClosure · Not started