PRJ-2026-001Off track4ExecutionHybrid

SCA ERP System

Remove from watchlist

One integrated system for the Authority’s finance, procurement and HR, connected to the Etimad platform.

Early warning: ⁦86%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 64.5M

Actual cost

SAR 44.7M

⁦69%⁩ of budget

Progress

⁦61%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 73.3M

SAR +8.8M

SPI · CPI

0.82Schedule performance index · 0.820.88Cost performance index · 0.88

Forecast finish

⁦2027-02-27⁩

58 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate7 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 November 2026Closure · Not startedClosure · Not started

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
SCA-PMO-F05
Template edition
2.0
Version
V2
Form date
⁦2025-02-06⁩
Hijri
7 Shaʻban 1446 AH
ApprovedPRJ-2026-001SCA ERP System

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-001
Project
SCA ERP System
Portfolio
Technology & Enterprise Systems Portfolio
Sector
Digital Transformation Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Dana S. Al-Saleh

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2025-01-12⁩

Baseline finish

⁦2026-12-31⁩

Forecast finish

⁦2027-02-27⁩

SPI

0.82

MilestonePlannedForecastSlip
Project plan approved⁦2025-06-22⁩⁦2025-09-26⁩+96 days
Designs approved⁦2025-10-24⁩⁦2026-04-12⁩+170 days
Build complete⁦2026-04-27⁩⁦2026-11-27⁩+214 days
Testing & acceptance complete⁦2026-08-29⁩⁦2027-01-12⁩+136 days
Final handover⁦2026-12-31⁩⁦2027-02-27⁩+58 days

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦5%⁩⁦2025-04-21⁩Dana S. Al-Saleh
Monitoring & reporting⁦4%⁩⁦2025-06-22⁩Munirah A. Al-Khalidi
Business requirements⁦10%⁩⁦2025-08-23⁩Munirah A. Al-Khalidi
Solution design⁦10%⁩⁦2025-10-24⁩Sarah A. Al-Qarni
Release 1⁦16%⁩⁦2025-12-25⁩Sarah A. Al-Qarni
Release 2⁦16%⁩⁦2026-02-25⁩Dana S. Al-Saleh
Integrations⁦11%⁩⁦2026-04-27⁩Munirah A. Al-Khalidi
System testing⁦8%⁩⁦2026-06-28⁩Dana S. Al-Saleh
User acceptance testing⁦8%⁩⁦2026-08-29⁩Munirah A. Al-Khalidi
Training & change⁦6%⁩⁦2026-10-30⁩Munirah A. Al-Khalidi
Go-live & handover⁦6%⁩⁦2026-12-31⁩Sarah A. Al-Qarni
Accepted with a certificate⁦61%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
RSK-0012Customisation and Etimad integration costs exceeding the approved contingency16EscalateDana S. Al-Saleh
RSK-0013Late migration and reconciliation of historical financial data12MitigateDana S. Al-Saleh
RSK-0014Implementation consultants’ contracts ending before go-live9MitigateMunirah A. Al-Khalidi

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyDana S. Al-Saleh
Project ownerDeliverable status and acceptance datesFortnightlyDana S. Al-Saleh
PMOData and indicator updatesWeeklyDana S. Al-Saleh
BeneficiariesWhat changes and whenAt each milestoneDana S. Al-Saleh
Team memberRoleAllocation
Dana S. Al-SalehProject manager⁦60%⁩
Eng. Asma S. Al-HamdanSCA ERP solution architecture⁦40%⁩
Haifa S. Al-RuwailiFinancial analyst⁦10%⁩
—Finance & procurement functional lead⁦100%⁩

5QualityAuto-filled

  • Peer review of every deliverable before acceptance
  • Written acceptance criteria for every deliverable
  • A PMO audit at every gate

6BenefitsAuto-filled

BenefitBaselineTargetOwner
No benefits recorded

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Dana S. Al-SalehDirector, Enterprise Systems & IntegrationSubmitted—⁦2025-02-06⁩ 11:56
2Methodology review — PMOMethodology reviewGhada A. Al-ShahraniPMO — analystApprovedComplete against the project management plan template.⁦2025-02-10⁩ 13:28
3Technical acceptance — project ownerTechnical acceptanceMunirah A. Al-KhalidiProject ownerApproved—⁦2025-02-13⁩ 14:35
4Cash flow & financial commitmentFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-02-17⁩ 12:51
5Plan aligned with the contractsFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2025-02-18⁩ 13:28
6Sponsor approvalTechnical acceptanceSarah A. Al-QarniProject sponsorApproved—⁦2025-02-23⁩ 11:56

Signatures

Methodology review — PMO

Ghada A. Al-Shahrani

Approved⁦2025-02-10⁩

Technical acceptance — project owner

Munirah A. Al-Khalidi

Approved⁦2025-02-13⁩

Cash flow & financial commitment

Munirah A. Al-Khalidi

Approved⁦2025-02-17⁩

Plan aligned with the contracts

Mazen A. Al-Hazmi

Approved⁦2025-02-18⁩

Sponsor approval

Sarah A. Al-Qarni

Approved⁦2025-02-23⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F05 · version V2

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Dana S. Al-Saleh on ⁦2025-02-06⁩

  1. Methodology review

    Methodology review — PMO

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-02-10⁩ at ⁦13:28⁩

    Complete against the project management plan template.

  2. Technical acceptance

    Technical acceptance — project owner

    Munirah A. Al-Khalidi · Project owner

    Approved · ⁦2025-02-13⁩ at ⁦14:35⁩

  3. Financial approval

    Cash flow & financial commitment

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-02-17⁩ at ⁦12:51⁩

  4. Financial approval

    Plan aligned with the contracts

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-02-18⁩ at ⁦13:28⁩

  5. Technical acceptance

    Sponsor approval

    Sarah A. Al-Qarni · Project sponsor

    Approved · ⁦2025-02-23⁩ at ⁦11:56⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-02-06⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Dana S. Al-Saleh

  2. V1Returned for edit⁦2025-01-23⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Dana S. Al-Saleh