PRJ-2026-001Off track4ExecutionHybrid

SCA ERP System

Remove from watchlist

One integrated system for the Authority’s finance, procurement and HR, connected to the Etimad platform.

Early warning: ⁦86%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 64.5M

Actual cost

SAR 44.7M

⁦69%⁩ of budget

Progress

⁦61%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 73.3M

SAR +8.8M

SPI · CPI

0.82Schedule performance index · 0.820.88Cost performance index · 0.88

Forecast finish

⁦2027-02-27⁩

58 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate12 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate7 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 November 2026Closure · Not startedClosure · Not started

Periodic update cards

Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.

Period

October 2026

In approvalDue todayAction time limit about to lapse · Limit 2 working days
Progress
⁦61%⁩
Planned
⁦74%⁩
SPI
0.82
Open the card

Periodic update cards

PeriodStatusProgressCurrent stepDate
October 2026UPD-001-2026-10In approval⁦61%⁩Methodology reviewDr. Noura M. Al-OtaibiDue todayAction time limit about to lapse · Limit 2 working days⁦2026-10-26⁩
September 2026UPD-001-2026-09Approved⁦58%⁩—⁦2026-10-02⁩
August 2026UPD-001-2026-08Approved⁦54%⁩—⁦2026-09-02⁩