PRJ-2026-005On track4ExecutionWaterfall

SCA Cybersecurity Programme

Add to watchlist

A security operations centre, identity & access management and full ECC compliance.

Budget (BAC)

SAR 38.6M

Actual cost

SAR 33M

⁦85%⁩ of budget

Progress

⁦88%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SAR 37.5M

SPI · CPI

1.02Schedule performance index · 1.021.03Cost performance index · 1.03

Forecast finish

⁦2026-12-10⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure22 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 December 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 February 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate22 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate22 October 2026Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

+1

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦88%⁩ done against ⁦86%⁩ planned.

SPI ⁦1.02⁩, CPI ⁦1.03⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: A Leading, Sustainable OrganisationSO-4.1Strong technical capabilities

Main initiative

SI-4.1.1Cloud & cybersecurity

Contribution to the initiative⁦16%⁩

The project’s share of the initiative’s project budget (3 projects)

Secondary links

No secondary links

Annual work-plan line
WP-2025-005
Classification
Operational

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦88%⁩

Awaiting acceptance ⁦6%⁩

Not handed in ⁦6%⁩

9 deliverables accepted

  • Release 1⁦14%⁩
  • Release 2⁦14%⁩
  • Integrations⁦14%⁩
  • System testing⁦10%⁩
  • User acceptance testing⁦10%⁩
  • Business requirements⁦9%⁩
  • Solution design⁦9%⁩
  • Project plan & baseline⁦4%⁩

1 deliverable under inspection or acceptance

  • Training & change⁦6%⁩

Progress & earned value

⁦4⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦91%⁩ of budget

33M/ 38.6M1.1Mprojected saving(⁦2.9%⁩)
Actual spend
33M
Committed
35.2M
Approved budget
38.6M
Estimate at completion
37.5M

Next milestones

  • Closure⁦2026-12-10⁩was ⁦2026-12-15⁩On track

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Change requests

Cost and schedule impact

  • No change requests

Risks & impediments

1 open risk, exposure SAR 3M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩1Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩RSK-0042Undetected vulnerabilities in legacy systems before SOC onboarding
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium1
  • Low0

Open impediments

⁦0⁩ escalated

  • No open impediments

Deliverables

⁦9⁩ of ⁦11⁩ approved

  • Project plan & baseline005-D1 · V1 · CRT-005-01⁦4%⁩Eng. Yasser M. Al-Zahrani⁦2025-05-07⁩2025-05-079 Dhuʻl-Qiʻdah 1446 AHApproved
  • Monitoring & reporting005-D2 · V1 · CRT-005-02⁦4%⁩Eng. Nayef H. Al-Buqami⁦2025-07-05⁩2025-07-0510 Muharram 1447 AHApproved
  • Business requirements005-D3 · V1 · CRT-005-03⁦9%⁩Eng. Nayef H. Al-Buqami⁦2025-09-01⁩2025-09-019 Rabiʻ I 1447 AHApproved
  • Solution design005-D4 · V1 · CRT-005-04⁦9%⁩Eng. Majed S. Al-Rasheed⁦2025-10-30⁩2025-10-308 Jumada I 1447 AHApproved
  • Release 1005-D5 · V1 · CRT-005-05⁦14%⁩Eng. Majed S. Al-Rasheed⁦2025-12-28⁩2025-12-288 Rajab 1447 AHApproved
  • Release 2005-D6 · V1 · CRT-005-06⁦14%⁩Eng. Yasser M. Al-Zahrani⁦2026-02-24⁩2026-02-247 Ramadan 1447 AHApproved
  • Integrations005-D7 · V1 · CRT-005-07⁦14%⁩Eng. Nayef H. Al-Buqami⁦2026-04-24⁩2026-04-247 Dhuʻl-Qiʻdah 1447 AHApproved
  • System testing005-D8 · V1 · CRT-005-08⁦10%⁩Eng. Yasser M. Al-Zahrani⁦2026-06-22⁩2026-06-227 Muharram 1448 AHApproved
  • User acceptance testing005-D9 · V1 · CRT-005-09⁦10%⁩Eng. Nayef H. Al-Buqami⁦2026-08-20⁩2026-08-207 Rabiʻ I 1448 AHApproved
  • Training & change005-D10 · V1⁦6%⁩Eng. Nayef H. Al-Buqami11 days overdue2026-10-176 Jumada I 1448 AHSubmitted
  • Go-live & handover005-D11 · V0⁦6%⁩Eng. Majed S. Al-RasheedIn 48 days2026-12-156 Rajab 1448 AHDraft

Team, contracts & documents

Team

2 members

Eng. Yasser M. Al-Zahrani · Director, CybersecurityEng. Hind A. Al-Zahrani · Munjaz Platform Administrator
  • Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityProject managerP-026y.alzahrani@sca.sa⁦50%⁩
  • Eng. Hind A. Al-ZahraniEng. Hind A. Al-ZahraniMunjaz Platform AdministratorPlatform engineer, cybersecurity programmeP-008h.alzahrani@sca.sa⁦20%⁩

Meetings

  • No meetings scheduled