Restricted
Kingdom of Saudi Arabia
Saudi Contractors Authority
Project Management Office (PMO)
- Code
- DOC-0222
- Version
- V1
- Date
- 2026-10-09
ECC compliance report — Q3
SCA Cybersecurity Programme
1. Executive summary
This report gives the position of SCA Cybersecurity Programme to date: 88% complete against 86% planned, SPI 1.02, CPI 1.03, and an estimate at completion of SAR 37.5M.
- Project
- SCA Cybersecurity Programme (PRJ-2026-005)
- Project manager
- Eng. Yasser M. Al-Zahrani
- Budget
- SAR 38.6M
- Progress
- 88% actual against 86% planned
- Forecast finish
- 2026-12-10
2. Key findings
- All planned milestones of the period met except one deferred
- Actual spend rose in line with the work done
- Three high risks under treatment, each with a named owner
3. Recommendations & decisions needed
- Approve the proposed treatment of the high risks
- Track the open findings with the vendor weekly
Prepared by
Eng. Yasser M. Al-Zahrani
Restricted