PRJ-2026-005On track4ExecutionWaterfall

SCA Cybersecurity Programme

Add to watchlist

A security operations centre, identity & access management and full ECC compliance.

Budget (BAC)

SAR 38.6M

Actual cost

SAR 33M

⁦85%⁩ of budget

Progress

⁦88%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SAR 37.5M

SPI · CPI

1.02Schedule performance index · 1.021.03Cost performance index · 1.03

Forecast finish

⁦2026-12-10⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure22 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 December 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 February 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate22 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate22 October 2026Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 38.6M split into spent, committed and left, with the estimate at completion

EAC SAR 37.5M
Revised request SAR 38.6M
  • Actual spendSAR 33M
  • Committed, not spentSAR 2.2M
  • Allotted, uncommittedSAR 2.2M
  • Contingency availableSAR 1.2M

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 39M
Original budgetwhen the first baseline was approved
SAR 38.6M
Approved budgetafter approved change requests
SAR 38.6M
Current budgetavailable to spend now
SAR 38.6M
Revised budgetif the pending changes are approved
SAR 38.6M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 35.2M
Contracts1 active contract
SAR 31.5M
Purchase orders⁦2⁩ orders
SAR 3.7M
Remaining budgetapproved less actual
SAR 5.6M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 33M
Accrualswork done, not yet invoiced
SAR 1.3M
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 37.5M
ContingencySAR 772K drawn of SAR 1.9M
SAR 1.2M

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 39M
ApprovedSAR 38.6M
Estimate at completionSAR 37.5M
Approved is SAR 400K (⁦1.0%⁩) below the estimate
The estimate at completion is SAR 1.5M (⁦3.9%⁩) below the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2024-11-19⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-61005
  • WBS elements⁦5⁩ elements · P-2026-005.01 …
  • Purchase orders⁦2⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦8⁩ posted · ⁦0⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 772K drawn of SAR 1.9M

  • Covering realised delivery risks⁦2026-08-29⁩SAR 772K

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance3.003.003.003.00⁦−0.00⁩
2Analysis & design6.376.376.376.37⁦−0.01⁩
3Build14.9814.9914.9914.99⁦−0.01⁩
4Testing & acceptance7.497.507.507.50⁦−0.01⁩
5Launch & handover5.623.351.125.04⁦+0.57⁩
Unallocated contingency1.160.000.000.58⁦+0.58⁩
Total38.6035.2032.9837.48⁦+1.12⁩

Budget split

WBS

SAR 38.6M

Budget

  • Management & governanceSAR 3M⁦8%⁩
  • Analysis & designSAR 6.4M⁦16%⁩
  • BuildSAR 15M⁦39%⁩
  • Testing & acceptanceSAR 7.5M⁦19%⁩
  • Launch & handoverSAR 5.6M⁦15%⁩
  • Unallocated contingencySAR 1.2M⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2027-04-06⁩+112

SPI(t) ⁦0.86⁩ against the approved finish ⁦2026-12-15⁩

Planned valuePV
SAR 37.8M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 34M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 33M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 38.6M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.99⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−3.81⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.03
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.90
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 37.5M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 4.5M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+1.12⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
0.82
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 37.5M
  • If the rest goes to planSAR 37.6M
  • At cost and schedule performanceSAR 38M
  • The PM’s bottom-up estimateSAR 37.5M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SAR 37.5M

Variance at completion: ⁦+1.12⁩ SAR M