Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-005On track4ExecutionWaterfall

SCA Cybersecurity Programme

Add to watchlist

A security operations centre, identity & access management and full ECC compliance.

Budget (BAC)

SAR 38.6M

Actual cost

SAR 33M

⁦85%⁩ of budget

Progress

⁦88%⁩Awaiting acceptance ⁦6%⁩

Estimate at completion

SAR 37.5M

SPI · CPI

1.02Schedule performance index · 1.021.03Cost performance index · 1.03

Forecast finish

⁦2026-12-10⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure22 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 December 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 February 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate22 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate22 October 2026Closure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

4Achieved
1On track
0At risk
0Late
Average delay38 days
Jul 25Oct 25Jan 26Apr 26Jul 26Oct 26Jan 27
Contractual
Build completePlanned: ⁦2026-04-24⁩Forecast / actual: ⁦2026-06-18⁩Delay: 55 daysG3 +55
Executive
Project plan approvedPlanned: ⁦2025-07-05⁩Forecast / actual: ⁦2025-07-23⁩Delay: 18 daysG1 +18
Payment
Final handoverPlanned: ⁦2026-12-15⁩Forecast / actual: ⁦2027-01-02⁩Delay: 18 daysG5 +18
Regulatory
Testing & acceptance completePlanned: ⁦2026-08-20⁩Forecast / actual: ⁦2026-10-26⁩Delay: 67 daysG4 +67
Project
Designs approvedPlanned: ⁦2025-10-30⁩Forecast / actual: ⁦2025-12-02⁩Delay: 33 daysG2 +33

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2025-07-05⁩⁦2025-07-23⁩⁦+18⁩ daysEng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@sca.saAchieved1Approved
Designs approvedMS-G2Project⁦2025-10-30⁩⁦2025-12-02⁩⁦+33⁩ daysEng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@sca.saAchieved1Approved
Build completeMS-G3Contractual⁦2026-04-24⁩⁦2026-06-18⁩⁦+55⁩ daysEng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@sca.saAchieved1Approved
Testing & acceptance completeMS-G4Regulatory⁦2026-08-20⁩⁦2026-10-26⁩⁦+67⁩ daysEng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@sca.saAchieved1Approved
Final handoverMS-G5Payment⁦2026-12-15⁩⁦2027-01-02⁩⁦+18⁩ daysEng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@sca.saOn track0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦88%⁩

Awaiting acceptance

⁦6%⁩

Not handed in

⁦6%⁩

Deliverable flow

Pick a stage to filter the register
⁦11⁩ results
Export CSV
Project plan & baseline005-D1⁦4%⁩CRT-005-01ApprovedEng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@sca.saEng. Nayef H. Al-Buqami⁦2025-05-07⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting005-D2⁦4%⁩CRT-005-02ApprovedEng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@sca.saEng. Nayef H. Al-Buqami⁦2025-07-05⁩V1⁦3⁩ of ⁦3⁩
Business requirements005-D3⁦9%⁩CRT-005-03ApprovedEng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@sca.saEng. Nayef H. Al-Buqami⁦2025-09-01⁩V1⁦3⁩ of ⁦3⁩
Solution design005-D4⁦9%⁩CRT-005-04ApprovedEng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.saEng. Nayef H. Al-Buqami⁦2025-10-30⁩V1⁦3⁩ of ⁦3⁩
Release 1005-D5⁦14%⁩CRT-005-05ApprovedEng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.saEng. Nayef H. Al-Buqami⁦2025-12-28⁩V1⁦3⁩ of ⁦3⁩
Release 2005-D6⁦14%⁩CRT-005-06ApprovedEng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@sca.saEng. Nayef H. Al-Buqami⁦2026-02-24⁩V1⁦3⁩ of ⁦3⁩
Integrations005-D7⁦14%⁩CRT-005-07ApprovedEng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@sca.saEng. Nayef H. Al-Buqami⁦2026-04-24⁩V1⁦3⁩ of ⁦3⁩
System testing005-D8⁦10%⁩CRT-005-08ApprovedEng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@sca.saEng. Nayef H. Al-Buqami⁦2026-06-22⁩V1⁦3⁩ of ⁦3⁩
User acceptance testing005-D9⁦10%⁩CRT-005-09ApprovedEng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@sca.saEng. Nayef H. Al-Buqami⁦2026-08-20⁩V1⁦3⁩ of ⁦3⁩
Training & change005-D10⁦6%⁩—SubmittedEng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@sca.saEng. Nayef H. Al-Buqami⁦2026-10-17⁩V1⁦1⁩ of ⁦3⁩
Go-live & handover005-D11⁦6%⁩—DraftEng. Majed S. Al-RasheedEng. Majed S. Al-RasheedHead, Digital Transformation SectorP-011m.alrasheed@sca.saEng. Nayef H. Al-Buqami⁦2026-12-15⁩V0⁦0⁩ of ⁦3⁩
Total · 11⁦100%⁩
⁦1⁩–⁦11⁩ of ⁦11⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close