PRJ-2026-005On track4ExecutionWaterfall
SCA Cybersecurity Programme
Add to watchlistA security operations centre, identity & access management and full ECC compliance.
Project managerEng. Yasser M. Al-ZahraniProject sponsorEng. Majed S. Al-RasheedProgrammeDigital Infrastructure & Security Programme
Budget (BAC)
SAR 38.6M
Actual cost
SAR 33M
85% of budget
Progress
88%Awaiting acceptance 6%
Estimate at completion
SAR 37.5M
SPI · CPI
1.02Schedule performance index · 1.021.03Cost performance index · 1.03
Forecast finish
2026-12-10
On baseline
ExecutionStage 4 of 5
Next gate:Closure22 October 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate4 December 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate2 February 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate22 May 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate22 October 2026Closure · Not startedClosure · Not started
Periodic update cards
Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.
Periodic update cards
| Period | Status | Progress | Current step | Date |
|---|---|---|---|---|
| October 2026UPD-005-2026-10 | Draft | 88% | — | 2026-10-26 |
| September 2026UPD-005-2026-09 | Approved | 83% | — | 2026-10-02 |
| August 2026UPD-005-2026-08 | Approved | 78% | — | 2026-09-02 |