SCA Cybersecurity Programme
Add to watchlistA security operations centre, identity & access management and full ECC compliance.
Budget (BAC)
Actual cost
85% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionStage 4 of 5
Next gate:Closure22 October 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate4 December 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate2 February 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate22 May 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate22 October 2026Closure · Not startedClosure · Not started
Project lifecycle and its gates
Current phase: Execution. Pick a gate on the track to review it.
- Gate into «Initiation»DecisionGoDate4 December 2024All criteria and required documents met.Pre-startComplete
- Gate into «Planning»DecisionConditional goDate2 February 2025Mandatory criteria met, with points to close during the next phase.InitiationComplete
- Gate into «Execution»DecisionGoDate22 May 2025All criteria and required documents met.PlanningComplete
- Gate into «Closure»DecisionNot held yetDate22 October 2026ExecutionCurrent stageCurrent stage
- 5ClosureNot started
What each stage requires
The documents and approvals each gate asks for before the next stage.
Closure gate — deliverables accepted and handed over
Gate readiness
Enough for a conditional go only
Automated control: no move until the criteria are met
- 3 mandatory checklist items open
- 2 required documents not approved
- 2 mandatory criteria under 70 points
- Weighted score 71 under the pass mark 75
Checklist
4 of 7 done
- Deliverable completion certificates approved for every deliverableMandatory
- Acceptance tests and handover to operations completeMandatory
- Open commitments listed with a plan to close themMandatory
- Deliverable-linked payments settledMandatory
- Pilot run with no critical or high findingsMandatory
- Users trained
- Launch rollback plan
Required documents
2 of 4 approved
- Deliverable completion certificatesNot submitted
- Project closure & handover formApproved · V1
- Lessons-learned logApproved · V1
- Benefits measurement planSubmitted — awaiting acceptance · V1
Criteria and score
Go from 75, conditional from 60; a mandatory criterion is met from 70.
Deliverables acceptedweight 35%Not met
Awaiting evidence from the project team.
Quality & securityweight 25%Not met
Awaiting evidence from the project team.
Operations & handover readinessweight 25%Met
Awaiting evidence from the project team.
User & training readinessweight 15%
Awaiting evidence from the project team.
Approvers
Project Management Office
- Dr. Noura M. Al-OtaibiPMO directorVote pending
- Eng. Nayef H. Al-BuqamiProject ownerVote pending
- Eng. Majed S. Al-RasheedProject sponsorVote pending