Saudi Contractors AuthorityMunjaz11My actionsNotifications

RSK-0020SCA Backup Data Centre

Late delivery of cooling units and standby generators

12MediumOpen

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Overlapping critical activities that depend on outside supplies and approvals

Preventive controls

  • Re-sequence critical activities and refresh the critical path
  • Weekly supply follow-up with the contractor

2 / 2

Event

Late delivery of cooling units and standby generators

12MediumTrigger

SPI under 0.85 two months running

Contingency

Extra shifts and fast-tracking the remaining works

Impact

Key milestones slip and indirect costs rise

SAR 3.2M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
12Medium

Residual

5
4
3
2
1
1
2
3
4
5
4Low

Exposure

SAR 3.2M

Residual

⁦67⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 7 days ago · Outside the engine — below «high»

  1. Project manager

    Current level

    Eng. Omar H. Bawazir

    Currently followed up here
  2. 2

    Programme manager

    Eng. Omar H. Bawazir

  3. 3

    PMO director

    Dr. Noura M. Al-Otaibi

  4. 4

    Executive committee

    Dr. Abdullah S. Al-Qahtani

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦2⁩ done
  • Re-sequence critical activities and refresh the critical path

    Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa
    In progressIn 33 days2026-11-3020 Jumada II 1448 AH
  • Weekly supply follow-up with the contractor

    Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@sca.sa
    Not startedIn 33 days2026-11-3020 Jumada II 1448 AH

Trigger

SPI under 0.85 two months running

Contingency

Extra shifts and fast-tracking the remaining works

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close